Wisconsin River TMDL Impacts

P R E S E N T E D TO T H E J O I N T R E G U L ATO RY ME E T I N G O F W I SC O N SI N C H E E S E MA K E R S A S S O C I AT I O N / MI DW E ST F O O D P R O C E S S O R S A S S O C I AT I O N - W IS C O N SI N D N R - F E B R U A RY 7 , 2 0 1 9 J O N B U T T S YMB I O N T P R O J E C T MA N A G E R

slide-2
SLIDE 2

Going to Tell a Story

The Beginning The New Permit What To Do?

slide-3
SLIDE 3

/

The Beginning

1

2012

New WPDES permit New total phosphorous (TP) limit

2

Before

3 mg/L

Now

2 to 0.93 mg/L

3

Timeframe

7 years

4

Met by 2017

Process changes Material substitutions

5

Relief

No need for adaptive management or nutrient trading

slide-4
SLIDE 4

The Beginning

1

2012

New WPDES permit New total phosphorous (TP) limit

2

Before

3 mg/L

Now

2 to 0.93 mg/L

3

Timeframe

7 years

4

Met by 2017

Process changes Material substitutions

5

Relief

No need for adaptive management or nutrient trading

slide-5
SLIDE 5

The Beginning

1

2012

New WPDES permit New total phosphorous (TP) limit

2

Before

3 mg/L

Now

2 to 0.93 mg/L

3

Timeframe

7 years

4

Met by 2017

Process changes Material substitutions

5

Relief

No need for adaptive management or nutrient trading

slide-6
SLIDE 6

The Beginning

1

2012

New WPDES permit New total phosphorous (TP) limit

2

Before

3 mg/L

Now

2 to 0.93 mg/L

3

Timeframe

7 years

4

Met by 2017

Process changes Material substitutions

5

Relief

No need for adaptive management or nutrient trading

slide-7
SLIDE 7

The Beginning

1

2012

New WPDES permit New total phosphorous (TP) limit

2

Before

3 mg/L

Now

2 to 0.93 mg/L

3

Timeframe

7 years

4

Met by 2017

Process changes Material substitutions

5

Relief

No need for adaptive management or nutrient trading

slide-8
SLIDE 8

In 2018, You Receive Notice of a New Permit

slide-9
SLIDE 9

Surprise! 5 Years to Comply

slide-10
SLIDE 10

More Surprises

When will the TMDL be finished? How does it impact this permit? What do I plan for?

slide-11
SLIDE 11

Let’s Compare

2012 Permit 2018 Permit

Original Limit

3 mg/L 0.93 mg/L

Interim Limit

2 mg/L 0.93 mg/L

Final Limit

0.93 mg/L 0.1 mg/L 6 mo. avg. 0.3 mg/L 1 mo. avg.

Compliance Plan Due

4 yrs 1 yr

Compliance Schedule

7 yrs 5 yrs

slide-12
SLIDE 12

But There is More From the Fact Sheet

Third year? No. The compliance schedule requires final plan in 1 year. Is the TMDL done?

slide-13
SLIDE 13

How About the TMDL?

TMDL sent to EPA December 2018 Mass Allocations Dependent on Criteria Used What do you Plan for? Example Current criteria: 0.939 lb/day Site specific criteria: 1.58 lb/day Current permit: 0.68 lb/day Current average: 6.36 lb/day

slide-14
SLIDE 14

So What do You Do?

Call the DNR to understand why? Call your lawyer? Call a consultant and ask for help? Call Ghostbusters?

slide-15
SLIDE 15

/

In Summary

1

Wisconsin River TMDL is confusing

2

Permit holders are pushed to make hasty decisions

3

You can only hope that you have been working with experts who have your best interests in mind

slide-16
SLIDE 16

1

Wisconsin River TMDL is confusing

2

Permit holders are pushed to make hasty decisions

3

You can only hope that you have been working with experts who have your best interests in mind

In Summary

slide-17
SLIDE 17

1

Wisconsin River TMDL is confusing

2

Permit holders are pushed to make hasty decisions

3

You can only hope that you have been working with experts who have your best interests in mind

In Summary

slide-18
SLIDE 18

/

Epilogue

You reach out for legal and technical help.

01

You apply for the MDV within 60 days

  • f permit issuance.

02

The MDV provides temporary relief from restrictive limits, allowing time for the TMDL issues to be resolved.