Connections Update
UR Connections Policy Call for Evidence Workshop Joint presentation by NIE Networks and SONI 12 December 2016
1
1 Outline Agenda Connections Market Overview Progress with - - PowerPoint PPT Presentation
Connections Update UR Connections Policy Call for Evidence Workshop Joint presentation by NIE Networks and SONI 12 December 2016 1 Outline Agenda Connections Market Overview Progress with Contestability at Distribution Status of
1
2 nienetworks.co.uk
2
3 nienetworks.co.uk
Generation < 5MW
generation applications in NI has resulted in an alternative application and offer process for generation connections http://www.nienetworks.co.uk/documents/Generation/Alterna tive-Connection-Application-and-Offer-P-(1).aspx
4 nienetworks.co.uk
4
5 nienetworks.co.uk
greater to the distribution network- this covers both generation and demand
Connections Provider (ICP) to undertake the ‘contestable’ work required for your connection or to ask NIE Networks to undertake all connection works.
in Northern Ireland
quotation for the work we will undertake.
costs and the different choices you have.
https://www.uregni.gov.uk/publications/decision-paper-contestability-electricity-connections http://www.nienetworks.co.uk/documents/Connections/Contestability-Guidelines-Version-2-2016-05-30.aspx
6 nienetworks.co.uk
7 nienetworks.co.uk
connections >=5MW from June 16
facilitate a competitive market for all new connections in NI in 2018
best practice
contestable and non-contestable works is a key priority for us
accepted
8 nienetworks.co.uk
550 1008 1000 1250 718
Constraints Vs Investment
500 1000 1500 2000 2500 3000 3500 MW
Min Load Max Load (c.1800 total)
Renewable Gen. System Load Transmission Capacity
Constraints Vs Investment
Connected Committed Achieving 25% (900 MW) Enabling 27% c.1000 MW under Medium Term Plan c.1726 MW Committed Max System Load c.1800 MW
*Predictions accurate based on current information at the beginning of December 2016
Phase 2
Phase 1 c.200 MW
c.1700MW Applications
9 nienetworks.co.uk
451 517 629 659 747 1164 1343 25 41 76 129 183 293 293
45 65 78 90 90
200 400 600 800 1000 1200 1400 1600 1800 2000 2012 2013 2014 2015 2016 YTD March '18 Beyond March '18 LSG(MW) SSG(MW) Micro(MW)
Potential Total Generation (Connected and committed) c.1726 MW
*Predictions accurate based on current information at the beginning of December 2016
c.1547 MW 1008 MW 853 MW 750 MW 562 MW 477 MW
10
– 10 Offers issued c120MW – 4 Contestable Offers issued
– 57 Offers issued c11MW
– 25 Offers issued c13MW
– Expect to commence issuing Offers very shortly
11
12
13
14 nienetworks.co.uk
AD Minimum Load WIND
PV
AD
PV
Minimum Load
WIND
PV
Zero Export
MEC Utilisation application Reduces min load Additional capacity by adding the min load assumption Reverse Powerflow Limit
Network Capacity (Tx or 33kV)
Additional capacity by investment in reverse Powerflow plant
Network Capacity (Tx or 33kV)
Network Overload No Reverse Power
– LSG Contestable Offers issued and being accepted – Working toward full market opening
– Good progress with Phase 1 release of Offers
– Impact on network
15