August 12, 2019 1:30 pm McLeod County North Complex Redetermination - PowerPoint PPT Presentation
COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65 August 12, 2019 1:30 pm McLeod County North Complex Redetermination Background JD 18 SM completed redetermination in November of 2016 Concerns with Outlet fee
COMBINED DITCH MEETING JD 18 SM JD 17 MS JD 32 SM Sibley CD 65 August 12, 2019 1:30 pm McLeod County North Complex
Redetermination • Background • JD 18 SM completed redetermination in November of 2016 • Concerns with • Outlet fee for JD 17 MS, paying over 9% of the benefits • Watershed boundaries do not match up to those previously redetermined • CD 65 boundary was extended to include portions of JD 18 SM • Redetermination stays in effect until another redetermination is complete • Total cost of the project was $1,033,395.89 • Cost less seeding and damages was $92,167.32
Redetermination • Proposed • Do a redetermination on JD 18 SM, JD 17 MS, JD 32 SM, Sibley CD 65 • Upon completion they are combined into 1 large system
Redetermination Including: • Process • Cost • Timeframe
Redetermination RECAP: • Eliminates current outlet fees • All 4 ditch systems, big or small, pay for the maintenance of the others • All acres are part of the system and watershed boundaries become seamless • CD65 and JD 18 SM boundary would no longer be an issue • Need to pay for the redetermination again • Drainage authority would be realigned to reflect the new benefit percentages • All expenses incurred up until ROB is final are spread on current benefits • Current debt on JD 18 SM is $647,637.50
Repair Projects Culvert Locations
Repair Projects Repair 18-176 256 th Lane Crossing
Repair Projects Repair 18-163 Heinz
Repair Projects Repair 18-081 Frauendienst
Repair Projects
Repair Projects
Repair Projects
Repair Projects
Repair Projects Contractor with lowest responsible bid: Wuetherich Drainage, Brian Wuetherich Sibley County culvert pieces have been delivered to the Gaylord area and are being assembled. Cost of pieces for 3 culverts: $49,551.000
256 th Lane Crossing • Significant flooding most springs • Impacts farm land upstream from culvert • Impacts farm land downstream from culvert • Impacts drivability of driveway east of 256 th Lane
256 th Lane Crossing March 20, 2019- looking east down 256 th Lane
256 th Lane Crossing March 20, 2019- looking NW into submerged ditch
256 th Lane Crossing March 22, 2019- looking south of 256 th Lane
256 th Lane Crossing March 22, 2019- looking east down 256 th Lane
256 th Lane Crossing March 22, 2019- looking NW into submerged ditch
256 th Lane Crossing May 28, 2019- looking west along 256 th Lane
256 th Lane Crossing • Solutions • Fix current 256 th Lane • Reroute the driveway
256 th Lane Crossing • Fix current 256 th Lane • 3 options from ISG Culvert Analysis, 2019 Option 1: • Install a 10’ x 8’ dual box culvert • Pros: • Increase the capacity of the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • Will protect the culvert which currently only has .89’ of cover • Total width of channel at culvert will be 22.5’ (currently 20’) • Cons: • Will not effect frequency of the road overtopping • Will overtop the road with any 25 year rain event • Cost: $152,840
256 th Lane Crossing • Fix current 256 th Lane • 3 options from ISG Culvert Analysis, 2019 Option 2: • Leave existing culvert • Pros: • Culvert is in good condition • Cons: • Will continue to flood
256 th Lane Crossing • Fix current 256 th Lane • 3 options from ISG Culvert Analysis, 2019 Option 3: • Raise the road 2 feet from elevation of 988 to 990 & install box culvert • Pros: • Increase the capacity of the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • Will protect the culvert which currently only has .89’ of cover • Total width of channel at culvert will be 22.5’ (currently 20’) • The lowest spot is the driveway is 300’ east of the culvert location, so building it up would prevent further flooding • Cons: • Will overtop the road with any 50 year rain event • Cost: $176,675
256 th Lane Crossing • Reroute the driveway • Pros: • Increase the capacity of 1895 the crossing • Lower the peak flood elevations upstream of the crossing by up to 3’ • The lowest spot is the driveway is 300’ east of the culvert location, so building it up would prevent further flooding • Cons: • Will overtop the road with any 50 year rain event • Cost: $60,000 minimum for construction • Maintain it perpetually
FEMA • Aaron met with Ryan from the Dept of Homeland Security & Emergency Management in May • Photos and hydraulic analysis have been sent to FEMA • FEMA hopes to be out as early as September to take a look at the damage/repairs • Improvements typically aren’t allowed unless it is more cost effective
Delta Feasibility Study
Two-Tier Ditches
Bonding Remaining principal & interest balance of debt: JD 18 SM – Redetermination: $234,150 (5 year, final payment 2/1/2023) Cleanout: $413,487.50 (20 year, final payment 2/1/2038) JD 32 SM – Improvement: $95,637.50 Call date: February 1, 2025 Bond defeasance is only option prior to this date, but fees/penalties
Bonding Future Bonding: Based on: $100,000 for redetermination $500,000 for culvert repairs $600,000 5 years at 1.5% up to 20 years at 2.25% Reimbursement Resolution: Look back 60 days from the date of the resolution & 18 months forward