Public-Private Transportation Partnership Board Board Meeting February 2 8 , 2 0 1 4 www.P3forPA.com 1 Approved Project Updates www.P3forPA.com 2 The Rapid Bridge Replacem ent Project Board Action: Approved September 2013 Procurem
SLIDE 1
SLIDE 2
www.P3forPA.com 2
Approved Project Updates
SLIDE 3
www.P3forPA.com 3
The Rapid Bridge Replacem ent Project
- Board Action: Approved September 2013
- Procurem ent Status:
– In February 2014, five teams submitted statements of qualification – 3 or 4 teams will be shortlisted in mid-March for the RFP – PennDOT expects to select preferred proposal fall 2014 – Construction expected to begin in summer 2015.
- Benefit to the Com m onw ealth: Replacement
- f 550-650 structurally deficient bridges.
SLIDE 4
www.P3forPA.com 4
The Rapid Bridge Replacem ent Project
- Com m onw ealth Bridge Partners: John Laing Investments, Fluor,
American Bridge Company, Traylor Bros. Inc., Joseph B. Fay Co., STV Incorporated and Infrastructure and Industrial Constructors;
- Keystone Bridge Builders: Macquarie, PCL, Conti Enterprises and
Stantec Consulting Services; and
- Keystone Bridge Partners: InfraRed Capital Partners, Kiewit, Parsons,
The Allan A. Myers family of companies, DBi and American Infrastructure;
- Pennsylvania Crossings: Meridiam, Lane Construction, AECOM,
Trumbull, Wagman Companies and Cofiroute.
- Plenary W alsh Keystone Partners: Plenary Group, The Walsh Group,
Granite Construction Company, HDR Engineering, HNTB Corporation and Infrastructure Corporation of America;
SLIDE 5
www.P3forPA.com 5
Sponsorship and Advertising Program
- Board Action: Approved January 2013
- Procurem ent Status: Contract Awarded
December 2013
- Private Partner: Travelers Marketing
- Benefit to the Com m onw ealth: Raise revenue
and offset cost of free service patrols, rest areas & welcome centers, 511 and other PennDOT and PA Turnpike services and programs.
SLIDE 6
www.P3forPA.com 6
5 1 1 Traffic and Traveler I nform ation
- Board Action: Approved January 2013
- Procurem ent Status: Contract Awarded
- Private Partner: Information Logistics
- Benefit to the Com m onw ealth: Info Logistics
will develop, operate and maintain the next gen 511 System for PennDOT with added functionality including hands free, eyes free notifications.
SLIDE 7
www.P3forPA.com 7
W ireless Telecom Partnership
- Board Action: Approved September 2013
- Procurem ent Status: A RFQ will be advertised
in spring 2014
- Benefit to the Com m onw ealth: Receive
revenue from telecom companies leasing space
- n existing PennDOT assets while also improving
wireless coverage for emergency response and PennDOT operations including Intelligent Transportations Systems (ITS) network.
SLIDE 8
www.P3forPA.com 8
Truck Perm itting and Routing System
- Board Action: Approved September 2013
- Procurem ent Status: A RFP is expected to be
advertised in spring 2014.
- Benefit to the Com m onw ealth: Procure a new
Automated Permit Routing Analysis System (APRAS) to manage application processing, route generation, route review and permit issuance of special hauling permits.
SLIDE 9
www.P3forPA.com 9
Projects Under Developm ent
SLIDE 10
www.P3forPA.com 10 10
Keystone Line Train Station Developm ent
- Status: A RFI was advertised on February 21st,
PennDOT will accept responses until March 17th.
- Benefit to the Com m onw ealth: Provide better
access to parking at these stations as well as
- ther upgrades and improvements.