Public-Private Transportation Partnership Board Board Meeting February 2 8 , 2 0 1 4 www.P3forPA.com 1 Approved Project Updates www.P3forPA.com 2 The Rapid Bridge Replacem ent Project Board Action: Approved September 2013 Procurem


slide-1
SLIDE 1

www.P3forPA.com 1

Board Meeting February 2 8 , 2 0 1 4

Public-Private Transportation Partnership Board

slide-2
SLIDE 2

www.P3forPA.com 2

Approved Project Updates

slide-3
SLIDE 3

www.P3forPA.com 3

The Rapid Bridge Replacem ent Project

  • Board Action: Approved September 2013
  • Procurem ent Status:

– In February 2014, five teams submitted statements of qualification – 3 or 4 teams will be shortlisted in mid-March for the RFP – PennDOT expects to select preferred proposal fall 2014 – Construction expected to begin in summer 2015.

  • Benefit to the Com m onw ealth: Replacement
  • f 550-650 structurally deficient bridges.
slide-4
SLIDE 4

www.P3forPA.com 4

The Rapid Bridge Replacem ent Project

  • Com m onw ealth Bridge Partners: John Laing Investments, Fluor,

American Bridge Company, Traylor Bros. Inc., Joseph B. Fay Co., STV Incorporated and Infrastructure and Industrial Constructors;

  • Keystone Bridge Builders: Macquarie, PCL, Conti Enterprises and

Stantec Consulting Services; and

  • Keystone Bridge Partners: InfraRed Capital Partners, Kiewit, Parsons,

The Allan A. Myers family of companies, DBi and American Infrastructure;

  • Pennsylvania Crossings: Meridiam, Lane Construction, AECOM,

Trumbull, Wagman Companies and Cofiroute.

  • Plenary W alsh Keystone Partners: Plenary Group, The Walsh Group,

Granite Construction Company, HDR Engineering, HNTB Corporation and Infrastructure Corporation of America;

slide-5
SLIDE 5

www.P3forPA.com 5

Sponsorship and Advertising Program

  • Board Action: Approved January 2013
  • Procurem ent Status: Contract Awarded

December 2013

  • Private Partner: Travelers Marketing
  • Benefit to the Com m onw ealth: Raise revenue

and offset cost of free service patrols, rest areas & welcome centers, 511 and other PennDOT and PA Turnpike services and programs.

slide-6
SLIDE 6

www.P3forPA.com 6

5 1 1 Traffic and Traveler I nform ation

  • Board Action: Approved January 2013
  • Procurem ent Status: Contract Awarded
  • Private Partner: Information Logistics
  • Benefit to the Com m onw ealth: Info Logistics

will develop, operate and maintain the next gen 511 System for PennDOT with added functionality including hands free, eyes free notifications.

slide-7
SLIDE 7

www.P3forPA.com 7

W ireless Telecom Partnership

  • Board Action: Approved September 2013
  • Procurem ent Status: A RFQ will be advertised

in spring 2014

  • Benefit to the Com m onw ealth: Receive

revenue from telecom companies leasing space

  • n existing PennDOT assets while also improving

wireless coverage for emergency response and PennDOT operations including Intelligent Transportations Systems (ITS) network.

slide-8
SLIDE 8

www.P3forPA.com 8

Truck Perm itting and Routing System

  • Board Action: Approved September 2013
  • Procurem ent Status: A RFP is expected to be

advertised in spring 2014.

  • Benefit to the Com m onw ealth: Procure a new

Automated Permit Routing Analysis System (APRAS) to manage application processing, route generation, route review and permit issuance of special hauling permits.

slide-9
SLIDE 9

www.P3forPA.com 9

Projects Under Developm ent

slide-10
SLIDE 10

www.P3forPA.com 10 10

Keystone Line Train Station Developm ent

  • Status: A RFI was advertised on February 21st,

PennDOT will accept responses until March 17th.

  • Benefit to the Com m onw ealth: Provide better

access to parking at these stations as well as

  • ther upgrades and improvements.