Capital Improvement Project Phase 3 and Capital Outlay Project Updates Tuesday ~ April 17 th , 2018 Board of Education Meeting Cheektowaga ~ Sloan Union Free School District Capital Improvement Project Phase 3 Renovations 2019 Theodore


slide-1
SLIDE 1

Cheektowaga ~ Sloan

Union Free School District

Tuesday ~ April 17th, 2018

Board of Education Meeting

Capital Improvement Project Phase 3 and Capital Outlay Project Updates

slide-2
SLIDE 2

Capital Improvement Project Phase 3

Theodore Roosevelt

* Roof Replacement * Roof Exhaust Replacement * Floor Replacement * Gym Wall Pad Installation * Emergency Lighting and Sensor

Upgrades

* Finish Upgrades

Woodrow Wilson

* Door Replacements * Locker Room Upgrades * Gym Wall Pad Installation * Hallway Locker Removals * Emergency Lighting and Sensor

Upgrades

* Nurse’s Office Renovation * Library and District Office Carpet

Replacement

Renovations 2019

slide-3
SLIDE 3

Capital Improvement Project Phase 3 Renovations 2019

JFK Middle / High School

* Tennis Court Replacement * Roof Exhaust Fan Replacement * Ceiling Replacements * Door Replacements * Toilet Room Renovations * Pool Ceiling Upgrades * Art Room Renovations * Music Suite Renovations * Main Office Renovations

Maintenance Garage / Team Room

* Shower Room Finish Upgrades * Roof Top Unit Replacement

slide-4
SLIDE 4

Cheektowaga ~ Sloan UFSD Schedule

slide-5
SLIDE 5

Cheektowaga ~ Sloan UFSD Budget

  • There is currently $3,641,935 remaining from Phase 1 and Phase 2 for this project.
slide-6
SLIDE 6

Theodore Roosevelt Elementary

Capital Improvement Project Phase 3

Gym Wall Pad Installation

slide-7
SLIDE 7

Woodrow Wilson Elementary

Capital Improvement Project Phase 3

Nurse’s Office Renovation

slide-8
SLIDE 8

Woodrow Wilson Elementary

Capital Improvement Project Phase 3

Gym Wall Pad Installation

slide-9
SLIDE 9

JFK Middle / High School

Capital Improvement Project Phase 3

Middle School Art Room Renovations

slide-10
SLIDE 10

JFK Middle / High School

Capital Improvement Project Phase 3

High School Art Room Renovations

slide-11
SLIDE 11

JFK Middle / High School

Capital Improvement Project Phase 3

High School Art Room Renovations

slide-12
SLIDE 12

JFK Middle / High School

Capital Improvement Project Phase 3

Music Suite Renovations

slide-13
SLIDE 13

JFK Middle / High School

Capital Improvement Project Phase 3

Toilet Room Renovations

slide-14
SLIDE 14

JFK Middle / High School

Capital Improvement Project Phase 3

Main Office Renovations

slide-15
SLIDE 15

JFK Middle / High School

Capital Improvement Project Phase 3

Middle School Main Office Renovations

slide-16
SLIDE 16

JFK Middle / High School

Capital Improvement Project Phase 3

Middle School Main Office Renovations

slide-17
SLIDE 17

JFK Middle / High School

Capital Improvement Project Phase 3

Middle School Main Office Renovations

slide-18
SLIDE 18

JFK Middle / High School

Capital Improvement Project Phase 3

High School Main Office Renovations

slide-19
SLIDE 19

JFK Middle / High School

Capital Improvement Project Phase 3

High School Main Office Renovations

slide-20
SLIDE 20

JFK Middle / High School

Capital Improvement Project Phase 3

High School Main Office Renovations

slide-21
SLIDE 21

Woodrow Wilson Elementary

Capital Outlay Project 2017-2018

Woodrow Wilson

* Finish upgrades to stairwells *Hallway handrails *Gym balcony handrails *Completion by June 2018

slide-22
SLIDE 22

Woodrow Wilson Elementary

Capital Outlay Project 2017-2018

Gymatorium Before:

slide-23
SLIDE 23

Woodrow Wilson Elementary

Capital Outlay Project 2017-2018

Gymatorium After:

slide-24
SLIDE 24

Woodrow Wilson Elementary

Capital Outlay Project 2017-2018

Stairwells Before:

slide-25
SLIDE 25

Woodrow Wilson Elementary

Capital Outlay Project 2017-2018

Stairwells After:

slide-26
SLIDE 26

We look forward to making great progress as we address your District’s needs.