Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd
TRIECA _ March 26-27th, 2013
Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd TRIECA _ March 26-27 th - - PowerPoint PPT Presentation
Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd TRIECA _ March 26-27 th , 2013 New Development ROW Upper Middle Road Retrofits Public Realm Green Glades Public Realm Beach Boulevard Park Retrofit ROW Retrofit
TRIECA _ March 26-27th, 2013
New Development ROW– Upper Middle Road Retrofits Public Realm– Green Glades Public Realm– Beach Boulevard Park Retrofit ROW Retrofit – Lakeview
Bioretention Unit New Development Oakville, Ontario Constructed in
Facility- 1,600m2 Accepts 4ha road
25mm event
to the habitat of Red-Side Dace, a fish species provincially designated as At Risk and protected under the Species at Risk Act (SARA).
approaches: Wet ponds, wetlands and OGS for water quality
discouraged
Hydrogeological Study of Groundwater - Surface
Previous Geotechnical reports – 05 & 07 Soil Stratigraphy
>8m of unsorted Sand & Gravel, overlain and confined within the valley slopes by 5‐10m of silty clay (Halton Till)
Hydraulic Conductivity
Silty Clay till –low conductivity (10‐7 to 10‐10 m/s) Sand & Gravel unit – high conductivity (10‐5 to 10‐6 m/s)
hand‐driven piezometers & sharp response to rainfall events and rapid drainage as baseflow
Seasonally High Groundwater Table Elevation
±122.5m
Groundwater Table Fluctuation
0.2‐0.5m
Plunge Pool Grass Filter Strip OGS Pre-Treatment
Bioretention Facility Underdrain System Overflow Channel
Native Sand & Gravel D-Washed 50mm ø Underdrains Media Shredded HW-Mulch Observation Well
Can be characterized by
representing the majority of the annual rainfall events, typically characterized by low intensity, long duration.
Can be characterized by
these types of events occur infrequently but are characterized by high intensity and short duration.
Bioretention Media is the functional component of the system – critical to the long-term function of the system
7.83 18 7.6 6.26 17.7 7.6 5.60 18.3 7.6 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 % Fines CEC (meq/100g) pH Prototype 1 Prototype 2 Prototype 3
Hand Mixed Prototypes
Mechanically Mixed Prototypes – Mass Production
7.83 18 7.6 7.7 15.6 7.5 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 % Fines CEC (meq/100g) pH Prototype 1 (Hand Mixed) Prototype 1 (Mechanically Mixed)
For Construction – Large Site
23.4 16.3 7.20 4.9 12.8 7.37 6.2 12.9 7.31 6.3 15.2 7.38 0.0 5.0 10.0 15.0 20.0 25.0 % Fines CEC (meq/100g) pH July 18, 2011 July 19, 2011 July 25, 2011 July 26, 2011
Infiltration Testing During Construction: 50-75mm/hr
Washed Un-washed
April 2012
June 2012
Bioretention Unit
Mississauga, ON Constructed in
Facility- 11m2 Accepts 0.03ha
25mm event
Drainage Area Retrofit Area
Pilot Project - Retrofit Accept runoff from the small flat roof above
Existing Issues
Guelph Permeameter – In-situ infiltration testing Sub-surface soils investigation – hand auger Soil Stratigraphy 10‐15cm of topsoil 0.8‐1.0m of Silty, Fine sand (approx 10% silt) >2m of Fine sand Hydraulic Conductivity At 1.5m depth below surface‐ hydraulic conductivity
Groundwater Table Elevation No water table encountered at depths greater than 2.5m throughout testing (June –August)
Bioretention Facility Dry River Bed Inlet Grate Outlet Grate Existing Electrical Trench
Existing Electrical Trench
Prelim liminary D Design Revised sed D Desi sign
For Construction – Small Site
7.7 15.6 7.5 25.9 15.2 7.5 13.4 14.8 7.6 0.0 5.0 10.0 15.0 20.0 25.0 30.0 % Fines CEC (meq/100g) pH Approved Media Mix (Mechanically Mixed) Refuted Sample (High) Refuted Sample (Low)
Be Before re
Af After
ROW Retrofit within older
Pipe System
filtration and infiltration
Mississauga, ON Construction – Spring
Accepts road & property
0.0 2.0 4.0 6.0 8.0 10.0 Alt Alternative R Rating Alt Alternatives
Public R ic Resp sponse ses t s to Presente ted A Alte ternatives
Support for
Grassed Swale Vegetated Swale Ditch Improvements
Third St.
7. 7.2m 2m w widths pro provides a access bu but is le is less t ss than cur current Ci City S Standard (8 (8.0m) Select cted t to r reduce ce im impervio ious co cover an and al allow f for addi dditional a area f for r bi bioswales
Geotechnical investigation undertaken within
Soil Stratigraphy 5‐30cm of topsoil 0.2‐1.5m of Clayey Silty Fill with some sand & gravel Clayey Silt Till deposits at depth Hydraulic Conductivity At 1.0‐1.2m depth below surface‐ design infiltration rate was determined to be 5.45mm/hr (2.5 SF) – 5mm/hr used in the design Groundwater Table Elevation Observations included generally no GW (GW observed at surface in some locations ‐ attributed to water perched in the ditches and fill stratum)
Water Service Line Punctured Bell Line Damaged (BellService Onsite)
To avo
Materials not identified in the geotechnical reports!
Re-grading of properties; Infil-development (3 homes); Abandoned and/or unmarked utilities; Sump-pump and property drainage
No trees;
Sacrificial Geotextile
Inlet ESC Controls
Soakaway Pit Park Redevelopment of
Hamilton, ON Constructed 2011 Accepts parking lot
Combined and separated
Seasonally high (March- April) groundwater elevation of 1.28m below the ground surface at an elevation of approximately 75.0m was determined