Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd TRIECA _ March 26-27 th - - PowerPoint PPT Presentation

chris denich m sc p eng aquafor beech ltd
SMART_READER_LITE
LIVE PREVIEW

Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd TRIECA _ March 26-27 th - - PowerPoint PPT Presentation

Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd TRIECA _ March 26-27 th , 2013 New Development ROW Upper Middle Road Retrofits Public Realm Green Glades Public Realm Beach Boulevard Park Retrofit ROW Retrofit


slide-1
SLIDE 1

Chris Denich, M.Sc., P.Eng Aquafor Beech Ltd

TRIECA _ March 26-27th, 2013

slide-2
SLIDE 2

 New Development  ROW– Upper Middle Road  Retrofits  Public Realm– Green Glades  Public Realm– Beach Boulevard Park Retrofit  ROW Retrofit – Lakeview

slide-3
SLIDE 3
slide-4
SLIDE 4

 Bioretention Unit  New Development  Oakville, Ontario  Constructed in

2011

 Facility- 1,600m2  Accepts 4ha road

drainage

 25mm event

slide-5
SLIDE 5
  • Designed and constructed to address stormwater impacts

to the habitat of Red-Side Dace, a fish species provincially designated as At Risk and protected under the Species at Risk Act (SARA).

  • General reluctance to approve conventional SWM

approaches: Wet ponds, wetlands and OGS for water quality

  • Facility that can be characterized/become habitat are

discouraged

  • Thermal impacts are now a concern
  • Disruption of baseflow, etc
slide-6
SLIDE 6

 Hydrogeological Study of Groundwater - Surface

Water Interaction (Aquafor, 2009)

 Previous Geotechnical reports – 05 & 07 Soil Stratigraphy

>8m of unsorted Sand & Gravel, overlain and confined within the valley slopes by 5‐10m of silty clay (Halton Till)

Hydraulic Conductivity

Silty Clay till –low conductivity (10‐7 to 10‐10 m/s) Sand & Gravel unit – high conductivity (10‐5 to 10‐6 m/s)

  • 2‐3 orders of magnitude difference
  • Using a sensitivity analysis, 15 mm/hr was determined using

hand‐driven piezometers & sharp response to rainfall events and rapid drainage as baseflow

Seasonally High Groundwater Table Elevation

±122.5m

Groundwater Table Fluctuation

0.2‐0.5m

slide-7
SLIDE 7

Bioretention Design

Plunge Pool Grass Filter Strip OGS Pre-Treatment

  • 1. OGS (Stormceptor STC 14000)
  • 2. Plunge Pool - 150m2
  • 3. Grass Filter Strip – 2.5m

Bioretention Facility Underdrain System Overflow Channel

slide-8
SLIDE 8

Bioretention Facility Design

Native Sand & Gravel D-Washed 50mm ø Underdrains Media Shredded HW-Mulch Observation Well

slide-9
SLIDE 9

 Can be characterized by

the rain event type: Sm Small Ev Event

  • Frequent/ ‘typical events’ –

representing the majority of the annual rainfall events, typically characterized by low intensity, long duration.

slide-10
SLIDE 10

 Can be characterized by

the rain event type: La Larg rge E Events

  • Infrequent/ Large Events -

these types of events occur infrequently but are characterized by high intensity and short duration.

slide-11
SLIDE 11

Bioretention Media is the functional component of the system – critical to the long-term function of the system

slide-12
SLIDE 12

7.83 18 7.6 6.26 17.7 7.6 5.60 18.3 7.6 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 % Fines CEC (meq/100g) pH Prototype 1 Prototype 2 Prototype 3

Hand Mixed Prototypes

slide-13
SLIDE 13

Mechanically Mixed Prototypes – Mass Production

7.83 18 7.6 7.7 15.6 7.5 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 % Fines CEC (meq/100g) pH Prototype 1 (Hand Mixed) Prototype 1 (Mechanically Mixed)

slide-14
SLIDE 14

For Construction – Large Site

23.4 16.3 7.20 4.9 12.8 7.37 6.2 12.9 7.31 6.3 15.2 7.38 0.0 5.0 10.0 15.0 20.0 25.0 % Fines CEC (meq/100g) pH July 18, 2011 July 19, 2011 July 25, 2011 July 26, 2011

slide-15
SLIDE 15

Infiltration Testing During Construction: 50-75mm/hr

slide-16
SLIDE 16
slide-17
SLIDE 17
slide-18
SLIDE 18
slide-19
SLIDE 19
slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23

Washed Un-washed

slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26
slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29
slide-30
SLIDE 30
slide-31
SLIDE 31

April 2012

slide-32
SLIDE 32

June 2012

slide-33
SLIDE 33
slide-34
SLIDE 34

 Bioretention Unit

Retrofit

 Mississauga, ON  Constructed in

2011

 Facility- 11m2  Accepts 0.03ha

road & roof drainage

 25mm event

slide-35
SLIDE 35

Drainage Area Retrofit Area

slide-36
SLIDE 36

 Pilot Project - Retrofit  Accept runoff from the small flat roof above

the building’s front entrance as well as a portion of the parking lot area

 Existing Issues

  • Iced sidewalk - Flat roof drainage flowed over

sidewalk area

  • Settlement of asphalt area at pedestrian cross-walk

created nuisance ponding and icy conditions

slide-37
SLIDE 37

 Guelph Permeameter – In-situ infiltration testing  Sub-surface soils investigation – hand auger Soil Stratigraphy 10‐15cm of topsoil 0.8‐1.0m of Silty, Fine sand (approx 10% silt) >2m of Fine sand Hydraulic Conductivity At 1.5m depth below surface‐ hydraulic conductivity

  • f native soils = 2.03x10‐3 cm/s or 73mm/hr

Groundwater Table Elevation No water table encountered at depths greater than 2.5m throughout testing (June –August)

slide-38
SLIDE 38

Bioretention Facility Dry River Bed Inlet Grate Outlet Grate Existing Electrical Trench

slide-39
SLIDE 39

Existing Electrical Trench

Prelim liminary D Design Revised sed D Desi sign

slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43

For Construction – Small Site

7.7 15.6 7.5 25.9 15.2 7.5 13.4 14.8 7.6 0.0 5.0 10.0 15.0 20.0 25.0 30.0 % Fines CEC (meq/100g) pH Approved Media Mix (Mechanically Mixed) Refuted Sample (High) Refuted Sample (Low)

slide-44
SLIDE 44
slide-45
SLIDE 45
slide-46
SLIDE 46

Be Before re

slide-47
SLIDE 47

Af After

slide-48
SLIDE 48
slide-49
SLIDE 49

 ROW Retrofit within older

residential area

  • Bioswales & Perforated

Pipe System

  • Permeable pavement
  • Bioretention media for

filtration and infiltration

 Mississauga, ON  Construction – Spring

2012

 Accepts road & property

drainage

slide-50
SLIDE 50
slide-51
SLIDE 51

0.0 2.0 4.0 6.0 8.0 10.0 Alt Alternative R Rating Alt Alternatives

Public R ic Resp sponse ses t s to Presente ted A Alte ternatives

Support for

  • Environ. Project

Grassed Swale Vegetated Swale Ditch Improvements

slide-52
SLIDE 52

(Most Important to least important) 1) Parking 2) Water Quality 3) Environmental Benefits 4) Prevent Flooding 5) Integration with the Environment 6) Improve Conveyance 7) Integration with Existing Infrastructure 8) Aesthetics Other results

  • No Sidewalks
  • Cost not important
  • Same Driveway width after

construction

  • 50% want perennial plants
  • Willing to do maintenance
slide-53
SLIDE 53
slide-54
SLIDE 54
slide-55
SLIDE 55
slide-56
SLIDE 56
slide-57
SLIDE 57
slide-58
SLIDE 58

Third St.

slide-59
SLIDE 59
slide-60
SLIDE 60

7. 7.2m 2m w widths pro provides a access bu but is le is less t ss than cur current Ci City S Standard (8 (8.0m) Select cted t to r reduce ce im impervio ious co cover an and al allow f for addi dditional a area f for r bi bioswales

slide-61
SLIDE 61
slide-62
SLIDE 62
slide-63
SLIDE 63

 Geotechnical investigation undertaken within

the existing ROW/ditches

Soil Stratigraphy 5‐30cm of topsoil 0.2‐1.5m of Clayey Silty Fill with some sand & gravel Clayey Silt Till deposits at depth Hydraulic Conductivity At 1.0‐1.2m depth below surface‐ design infiltration rate was determined to be 5.45mm/hr (2.5 SF) – 5mm/hr used in the design Groundwater Table Elevation Observations included generally no GW (GW observed at surface in some locations ‐ attributed to water perched in the ditches and fill stratum)

slide-64
SLIDE 64
slide-65
SLIDE 65
slide-66
SLIDE 66
slide-67
SLIDE 67
slide-68
SLIDE 68

Water Service Line Punctured Bell Line Damaged (BellService Onsite)

slide-69
SLIDE 69

 To avo

avoid an an ex existing gas gas lin line, a a section o

  • f

perforated und underdrain was no notched t to a allow th the g e gas l line to to tra transect th the pi e pipe

slide-70
SLIDE 70
slide-71
SLIDE 71

Materials not identified in the geotechnical reports!

slide-72
SLIDE 72
slide-73
SLIDE 73
slide-74
SLIDE 74

 Re-grading of properties;  Infil-development (3 homes);  Abandoned and/or unmarked utilities;  Sump-pump and property drainage

connections;

 No trees;

slide-75
SLIDE 75

Sacrificial Geotextile

slide-76
SLIDE 76

Inlet ESC Controls

slide-77
SLIDE 77
slide-78
SLIDE 78
slide-79
SLIDE 79

 Soakaway Pit  Park Redevelopment of

vacant land

 Hamilton, ON  Constructed 2011  Accepts parking lot

drainage for up to 100 year storm (full infiltration)

 Combined and separated

storm sewers – City desire to minimize flows resulting from infill developments

slide-80
SLIDE 80

Groundwater – Seasonally High Infiltration Testing Sands and Gravel

Seasonally high (March- April) groundwater elevation of 1.28m below the ground surface at an elevation of approximately 75.0m was determined

slide-81
SLIDE 81

Groundwater – Seasonally High = Major Design Concern due to site location

slide-82
SLIDE 82
slide-83
SLIDE 83
slide-84
SLIDE 84
slide-85
SLIDE 85