CNS In-pile Replacement Project W. Bermudez and A. Eltobaji - - PowerPoint PPT Presentation

cns in pile replacement project
SMART_READER_LITE
LIVE PREVIEW

CNS In-pile Replacement Project W. Bermudez and A. Eltobaji - - PowerPoint PPT Presentation

CNS In-pile Replacement Project W. Bermudez and A. Eltobaji December 2017 What is the project? To replace the Cold Neutron Source (CNS) as it is approaching the end of its design life. The CNS In-Pile is a 3m tall structure and it goes


slide-1
SLIDE 1

CNS In-pile Replacement Project

  • W. Bermudez and A. Eltobaji

December 2017

slide-2
SLIDE 2

CORE PCS PIPE

The CNS In-Pile is a 3m tall structure and it goes here

CRYO-PIPE

What is the project?

  • To replace the Cold Neutron Source (CNS) as it is

approaching the end of its design life.

slide-3
SLIDE 3

Why do we need to replace it?

  • Moderator vessel is made from AlMg5.
  • Thermal neutrons cause damage to Al

alloys through transmutation – Al transmuted to Si.

  • Si is insoluble in Al and will form particles
  • r potentially Mg2Si particles – solution

hardening.

  • Fast neutrons displace Al atoms from their

initial lattice position => point defects and dislocations => more susceptible to cracking.

slide-4
SLIDE 4

Life extension of the CNS In-pile

  • Manufacturer’s rated design life is 10

years at full power. This will come in early 2019.

  • No real data for AlMg5 in this

environment for >10 years operation.

  • NSTLI – Materials - report concluded

that manufacturing defects and/or

  • perational defects are not likely to be
  • f sufficient size to result in critical

crack instability after 15 years of

  • peration.
  • weld residual stress (WRS) and the decreasing irradiation

toughness are the major parameters in determining critical crack sizes.

slide-5
SLIDE 5

Installation schedule

Project Initiation and Scoping Phase

We are here 2014 Target 2015 2016 2024 2018 2017

Design and Build Phase Initiate and Scoping Concept design Manoeuvre definition Funding Case Detailed Engineering – In-pile and mockup Construction and procedure development RFT

2023

Installation Phase Licensing Training Installation

Long Shutdown

Documentation

slide-6
SLIDE 6

CNS Mk2 – how is it different?

  • Conceptual designs based on calculations

benchmarked by measurements.

  • Possible gains of 11% to 35% in source

brightness at the long wavelengths (> 8Å).

0,90 1,00 1,10 1,20 1,30 1,40 1,50 2,00 4,00 6,00 8,00 10,00 12,00 14,00 Ratio Wavelength λ (Å) case2 case3 case4

Case 1 as reference datum

Case 3 was selected

slide-7
SLIDE 7

Manoeuvre development - Constraints

1. ANSTO dose limit – 15 mSv/year per person 2. Project dose constraint – 10 mSv for any individual 3. Project dose target – 5 mSv per person 4. Design target – 2.5 mSv per person

  • CNS Replacement project - 25 mSv.man
  • Expect to need 9 persons minimum (based on radiation

dose). Fatigue, dehydration, etc. may affect this number.

  • Expect to operate on 2 extended shifts (10 hours) per day

(this setup was used successfully with Cold Guide 2 installation in 2012).

slide-8
SLIDE 8

The original CNS installation

slide-9
SLIDE 9

What is different now?

Need to remove these nuts 120mSv/hr at contact! Need to remove all the pipework and support bracket in order to remove the CNS in-pile Background radiation ~100µSv/hr. (Based on previous tasks) Likely radioactive contamination everywhere!

The top flange of the CNS is here

There will be residual heat within the walls It’s a confined space!

slide-10
SLIDE 10

Manoeuvre development methodology

1. ALARA 2. High automation (low dose, complexity and cost) vs low automation (higher dose, less complexity) 3. Some tasks would be hard to automate e.g. welding pipes, removing certain nuts with limited access, seal groove preparation, etc. 4. The decision was to automate repetitive tasks and manually perform the complex

  • tasks. This means using distance (long

tools), shielding and optimising the duration

  • f the tasks.
slide-11
SLIDE 11

Manoeuvre development

  • Manoeuvre development step-by-step in

mock-up (no radiation PPE)

  • Manoeuvre development step-by-step in

mock-up (with radiation PPE) (with ANSTO WHS and Radiation protection assistance)

  • Abnormal operations and recovery

scenarios

  • Training before installation

Simulation of rescue scenarios

slide-12
SLIDE 12

5 main steps to the manoeuvre

1. Reactor shut down, process set up for opening and Level 13 preparation (pool top area)

  • Purge the lines, bring components and

tools to Level 13

  • Remove silicon rack, protection covers

and other sensitive equipment

  • Line the area with plastic

2. CNS removal, CNS disassembly and final storage 3. New CNS assembly and reactor pool preparation 4. New CNS installation in reactor pool 5. CNS testing, cold and hot commissioning

slide-13
SLIDE 13

Removal of the existing CNS

  • Shielded workbox

for a person to enter the pool.

  • Use the water as

shielding.

  • Drop water level to

as low as +4300 (just under the CNS flange) depending on the task.

Need to cut pipes here

slide-14
SLIDE 14

Removal of the existing CNS

  • Shielded workbox can be

configured for different tasks.

slide-15
SLIDE 15

Removal of the existing CNS

Cutting of vacuum and deuterium lines – improvements for future replacements. Disconnection and cutting of heavy water lines – improvements for future replacements.

slide-16
SLIDE 16

Removal of the existing CNS

CNS flange unbolting/bolting

slide-17
SLIDE 17

Removal of the existing CNS

Attachment of lifting equipment to CNS

Overall weight of assembly ~600kg

slide-18
SLIDE 18

CNS Pipework Disassembly

LEVEL 13 LEVEL 10 Pool wall Control Room wall CNS Storage Pipework for the new CNS in-pile is assembled here too. Shielded support

slide-19
SLIDE 19

CNS Installation – Alignment device

Electrical cylinder Guides for CNS (polypropylene) 100 mm lead Shielding ~300 kg CNS ready for insertion

slide-20
SLIDE 20

CNS Installation – lifting of new CNS

New pipe support frame and lifting device to allow for one motion insertion.

slide-21
SLIDE 21

Mock-up of reactor pool and CNS

  • Mock-up built - Full-scale ½ pool
  • To be used to develop the procedure.
  • Will be used to train technicians
slide-22
SLIDE 22

Mock-up of reactor pool and CNS

  • Development of the manoeuvre has

commenced.

slide-23
SLIDE 23

Thank you