Crowned Ridge Wind Project South Dakota PUC Public Input Hearing Waverly, South Dakota March 20, 2018 Applicant overview Crowned Ridge Wind, LLC (CRW) is a wholly owned, y CC 0 ned ro e a 0 indirect subsidiary of
Applicant overview
► Crowned Ridge Wind, LLC (CRW) is a wholly owned,
indirect subsidiary of NextEra Energy Resources, LLC (NEER)
► American owned and operated, NEER is the world’s
largest generator of renewable energy from the wind and sun
► NEER affiliates own and operate 118 wind farms across
the United States and Canada
► NEER currently owns and operates
three wind farms in the state of South Dakota
» South Dakota Wind, Day County Wind and Wessington Springs
1
generator of wind and solar energy 2018
world’s
#
2
►
ro e
CC
a
y
0 ned
1 n
e
u
1a y of e t ra
er y e o rce
LLC EE
►
mer1 a
ed a perated,
EE
t e
0 d
a e
g
era ro ren a lee e y from he
I
n
►
EE
a 1
1 a
- n a d pera e 1 8
n far aero e n te ta e a anada
►
EE
C
ently o a d pera e r e
dam
the ate o Oak a
) )
Dao a
I
d D a y C
- y
a
d
e
I
t
- n
pr1 g
Project overview – current filing
» Crowned Ridge Wind, LLC
PUC filing date:
- Jan. 2019
PUC Status: Under review » CRW is seeking Facility Permit approval to construct, own and operate the up to 300 MW Crowned Ridge Wind project » CRW possesses a Power Purchase Agreement (PPA) with Northern States Power (NSP) » The Project is a $400 million investment in the state of South Dakota and located in Codington County and Grant County, SD » The Project has a proposed Commercial Operations Date (COD) of December 2019
3
164S@
Waverly
MyersL~ NEProject overview – purpose of project
► Crowned Ridge Wind, LLC is seeking Facility permit approval for the proposed
up to 300 MW Crowned Ridge Wind Farm located in Codington County and Grant County, South Dakota …..
» To satisfy energy demands within NSP’s service territory by delivering zero-emission, competitively priced electricity to the Midcontinent Independent System Operator, Inc (MISO) regional grid.
› Demand was recognized by the Minnesota Public Service Commission and North Dakota Public Service Commission
» To supplement NSP’s pursuit of a higher renewable energy generation mix across their generation output/consumption portfolio » To deliver a safe and reliable project to Codington and Grant County compatible with existing land uses, provides additional revenue streams, creates jobs and yields local benefits
4
►
Cro e dge
I
L c, ee 1 g Fac1l1 y er 1t a p o al or e ro o e p o 30 Cro d e d arm oca e Co
1 n
Cou ya Gra C u y h Dao a
- To
fy e ergy ema d
1t
p
erv1ce t rr1 ory by
- ))
a
I
ever g ze o-e
10n
co e 1 1 ely r ce elec r1c1 y o the
1dcon 1nen lndepe den
Y
e Ope a or
C
I O reg o al grid
>
De and wa recogn ze by he M1 ne ota Public erv ce Comm1
- n and
- rt
D a
- a
P bllc e ice Comm io
>>
x aero heir g
>> To
Jobs and yie s lac
NEXTera
~
ENERGY~
Project overview – why now?
► Crowned Ridge Wind, LLC elected to file the Crowned Ridge Wind Facility Permit
application in January 2019 for a number of reasons:
» Both Codington County and Grant County have completed the review process of the existing local ordinances and successfully codified new siting requirements for Wind Energy Systems » CRW has completed the necessary field surveys and micrositing of Project infrastructure and adopted changes to the Project site plan to ensure compliance with the newly codified county siting requirements for Wind Energy Systems » Land easements have been obtained for 99% of the Project’s proposed infrastructure » The South Dakota PUC’s application review process reflects a 6-month approval timeline which supports the Project’s proposed COD of December 2019
5
►
Cro ne d e
I
C elec e
- 1le
e C ed
1dge F a c 1 I I y Per 1
app 1cat o
n an ary 2 9 f r a n ber o r a o
>>
- h Cod g on Co
ty a Gran Co ty ha e com leted t e re 1e r c
- f
e
e x 1
1 g I ca
- r
na ce an cce fully cod fie e
tI g re
ire e for Wind E e gy y em C a co le ed he nece a y e d rvey a d cro
I g f Pr Jee
1 f a r cture a ado te c a ge
- e ProJec
Ite plan o en ure co p 1 a n c e
1 h
e e ly co 1f e cou y 1t1ng re u1remen fo
1n
E er y y em
>> La d e
e e have een o a ed for 99°/o o t e ProJec pro o e
I
a r c ure
>> The o
Da o a PUC ap Ilea 10n ev1e pr ce reflec a -
- t me ne
c upport t e P oJec propo ed COD of Dec
NEXTera
~
ENERGY~
Project overview – site plan
» Project Size: 300 MW » Project Area: 53,186 acres » Participation: 45,935 acres » Project Turbines: 130 GE 2.3 MW turbines
» (117) 2.3 MW 116-90 at 485’ total height, (13) 2.3 MW 116-80 at 452’ total height; and (20) alternate turbine locations » 95 turbines proposed in Codington County; 35 turbines proposed in Grant County
» Other Project Facilities:
» Access roads to project facilities, underground collection cabling and an Operations and Maintenance (O&M) Facility
6 Strandburg
Community Benefits
► Boost to local economy
» 250 temporary construction jobs will increase local spend (hotels, dining, places to conduct general business) » 7-12 full time, long term O&M jobs created for the life of the project » $400 million investment in the state
- f South Dakota
► Landowner benefits
» Approx. $40 million in payments to landowners over life of the project » Improvements to existing county and township roads
7
2
7 2
NEXTera~
E ~
Community Benefits
8
Crowned Ridge Wind Project – 25 year Expected Tax Revenue
Jurisdiction Estimated Total Tax Revenue Grant County $2,170,000.00 Codington County $4,880,000.00 Mazeppa Township $30,000.00 Twin Brooks Township $40,000.00 Stockholm Township $30,000.00 Troy Township $60,000.00 German Township $90,000.00 Leola Township $280,000.00 Waverly Township $400,000.00 Rauville Township $50,000.00 Waverly School District $26,150,000.00 Milbank School District $3,190,000.00 $37,370,000.00
NEXTera~
~
Community Benefits
► Local support of organizations,
groups and events
► Crystal Springs Rodeo ► South Dakota Wind for Schools program ► Kite Day at the Capitol ► SDSU Wind Application Center ► Mitchell Tech / Lake Area Tech ► Molded Fiber Glass (Aberdeen, SD)
New contract keeps MFG open; 60 jobs to be added
By Elisa Sand, esand@aberdee.nne, s.com Jul 2, 20 8
..._, 0
1 min to read
Stakeholder outreach
► Crowned Ridge Wind’s stakeholder outreach has resulted in 99% completion in
land acquisition (no eminent domain utilized)
► Stakeholder outreach involved communication with landowners, local tribes,
wildlife agencies and government officials:
» Codington County Planning and Zoning » Grant County Planning and Zoning » Sisseton Wahpeton Oyate Tribe » Spirit Lake Tribe » United States Fish & Wildlife Service » South Dakota Game, Fish & Parks » Open House conducted on Nov. 16th 2017
10
►
C r
- n
e d
R d
e W1 d a k e h
- l
d e r
- u
t r e a c h h a r e u l e d In
9 9 ° /
- c
- m
p l e t i
- n
In I a n ac u
10n (no e
I
e d
- m
a 1
u t 1 I
z e d )
►
t a e
- l
er
- t
r e a c h n v
- v
e d c
- u
n I c a t I w i t h a downer l
- c
a l r b e s w I d i f e a g e n c I e a d g
- v
e r n m e
- ff1c1a :
. . ,
>> Co Ington County P an Ing and Zon1 g > >
G r a n C
- n
y P i a n I n a n d Z
- n
· n g
>>
·s e o Wahpe o Oyate Tribe
>>
pir1 Lake Tribe
> >
U n i t e d t a t e s
F 1
h & W 1 l d l i e e r v c e
>> So th Dako a Game
F 1
h & P a r k
>> Ope Hou e conduced on
- v
1 6
h
2 1 7
ENERGY~
~
General Project Location Selection
► Available wind energy resource
» Wind resource data confirms viable wind resource suitability of Project Area
► Access to viable transmission interconnection
» Adequate proximity to the Big Stone South Substation with suitable infrastructure and available capacity
► Landowner support for wind energy development
» Voluntary participation from approx. 86% of all lands located within Project Area some of which have been participating for 10+ years
► Land use and environmental resource compatibility
» Project layout supplements existing land uses and avoids or minimizes the impacts to natural and cultural resources
11
►
A a1la
>> W d e ource a a co firm
ab e ind re ource u1
a b 1 1 t y
- f ProJect Area
Acee
- a e ra
erconnect on
>>
de u te prox1 1 y o
- e
- ub
a
10n
t a available capacity
Lando er p for
>> Vol ntary pa 1c pa on om a p ox 86°/o of all an
- cate
- me of h ch ha e bee
p a
1 c
pa 1ng for 1
O+ year
►
La e a e
- e a r
- ce ompat
1 1 y
>> ProJec layo t uppleme
t
ro ect Area ac s
NEXTera
~
ENERGY~
Project Compliance
► CRW has worked diligently to make the necessary changes to the Project site
plan to meet and exceed local and state wind energy siting requirements
12
Section 5.22.03 General Provisions - Codington County Requirements Setbacks
550’ from participating occupied residence, business, church, or school
1,500’ from non-participating occupied residence, business, church, or school (within all Districts other than Town Districts)
5,280’ from Municipal Boundaries at the time of Conditional Use Application
110% of the height of the wind turbine from Right-of-Way of public roads
110% the height of the wind turbines from any property line Noise
- Shall not exceed 50 dBA, average A-weighted Sound pressure level effects at the property line of
existing non participating residences, businesses, and buildings owned and/or maintained by a governmental entity Flicker Analysis
- Flicker at any receptor shall not exceed thirty (30) hours per year within the analysis area for all
schools, churches, businesses and occupied dwellings within a one (1) mile radius of each turbine within a project.
NEXTera~
~
Project Compliance
13
Section 1211.0 General Provisions - Grant County Requirements Setbacks
1,500’ from participating residence, business, church, or school, building owner and/or operated by a governmental entity
1,500’ from non-participating residence, business, church, or school, building owned and/or
- perated by a governmental entity
5,280’ from Municipal Boundaries existing at the time of Conditional Use Permit Application
500’ or 110% of the vertical height of the wind turbine, whichever is greater, from Public ROW
500’ or 110% of the vertical height of the wind turbine, whichever is greater, from any property line Noise
- Shall not exceed 45 dBA, average A-weighted Sound pressure including constructive interference
effects measured twenty-five (25) feet from the perimeter of the existing non-participating residences, businesses, and buildings owned and/or maintained by a governmental entity.
- Shall not exceed 50 dBA, average A-weighted Sound pressure including constructive interference
effects measured twenty-five (25) feet from the perimeter of participating residences, businesses, and buildings owned and/or maintained by a governmental entity. Flicker Analysis
- Flicker at any receptor shall not exceed thirty (30) hours per year within the analysis area for all
schools, churches, businesses and occupied dwellings within a one (1) mile radius of each turbine within a project.
NEXTera~
~
Wind farm description
► The project will consist of up to 130 turbines, a collector substation, under ground
collection lines and an O&M facility: » Turbines – 117 GE 2.3 MW, 90m HH and 13 GE 2.3 MW 80m HH » Collector substation – 34.5kV to 230kV fenced area with breakers, switches,
control house and two power transformers
» Underground collection lines – 34.5kV power cables buried at least 36 inches
below the surface that connects the turbines to the substation. It also includes pad mount transformers and junction boxes
» O&M facility – Fenced area with a main building that accommodates offices,
spare parts storage, maintenance shop and parking facilities
14
►
The proJe
II co
urb1 e
a colle o
b a
1 n
u der ro nd
- lee 10
1 e an
))
- 117 GE 2 3
90
Han
3 GE 2 3 H
C II co
a on-3
0 23
e ced a ea a e
IC e
co ro
- u e and
- o er ran for e
U d g o d col e io
belo he u ace a mo tran former a
)) 0
e - 34 5
po er cab e Ie a lea 3 1 c he
r b 1 n e
to he ub tat o I
- include pa
boxe
........,...3-1~ '"' ommoda es office
g ac'li · e s
NEXTera
~
ENERGY~
Construction overview
► The construction process begins with a detailed engineering design for all the
facets of the project including; access roads, turbine foundations, tower erection and electrical systems
► Turbine foundation
» Remove and stockpile top soil for future reclamation » Install straw waddles and silt fences to control run-off during rain events » Excavate turbine foundation to approx. 8’ depth » Install rebar and bolt cage » Pour concrete supplied by on-site batch plant
15
►
e co r c o pr
e91
1t a e ail d
9 1
ee n9 e
1 9
for all fa e
- f he proJe
1n I
n a ce road r
I
e fo n a 10
- e er
a d lee r1 al y m
ato
>
emo e and tockp1le o
- I for fu re ecla at n
.----------------
) all t a a die a d ence
- con rol
run off during ra1 e en
~ ~ ~ " ' "
- ~
~ i t . ~
>> E ca a e urb1 e fo nda 10
- appro
8 ep h ~-
> I
all e ar a d bot cage Po r concre e pp 1ed by o - e ba c pla
NEXTera
~
E ~
Construction overview
- Turbine towers are erected using special cranes that
are capable of lifting up to 1,800 ton and reaching a height of 350 feet (107 meters)
- Install down tower assembly including turbine
converter
- Install tower base including torqueing anchor bolts
- Install mid and top tower sections
- Install nacelle, hub and fly rotor
16
, T r
e to er re e ec ed
- at
I
ec1a
ra e a a le
- 0 1
are
I I
a e a c
n a
heig
- f 35 fee 1 7
e er
,I all
e a e by I cl din r 1ne co ve r
e
a e cl
ng or ue g a c or ol e ec 10n
NEXTera
~
Construction overview
- The collection lines are installed using a trencher or
horizontal direction bores
- Cables and communications line are simultaneous laid
while trench is being cut
- Trenches are back filled with native soil and compacted
- The collector substation is designed, constructed to meet
all the applicable codes and standards
- Clear and grub site, grade and compact site, install below
grade infrastructure, equipment foundations, equipment, wire and termination, test and commissioned equipment
17
e callee 10n
I
e are
1 n
alle u
I
g a tre c e or
Cable an co n ca I0n I e are
I ul a eo
aid hile re c
I
eIn cu
, T enche are ac
I ed I
na I e 011 and compacte
, T e col ec or u
at10
tr c e ee a I e a
p I ca I
e co
, Clear an rub
I e grade a d co pac I e, 1
a belo grade i f a r c ure equ pme t fou a 10n equip en ire a d er
I a I0n e
a comm 1oned quip e t
..
NEXTera
~
ENERGY~
Operations overview
► The project will be monitored 24/7 from the Renewable Operations Control
Center by a SCADA system. In addition the site will be maintained and monitored locally from the O&M building by 12 wind technicians, technician site lead and a site manager
» Supervisory Control and Data Acquisition (SCADA) system collects real time data from wind farm and substation and feed information to controllers located in the turbine and substation » Controllers make automatic adjustments based on set points established for the safe, reliable and efficient operation of the site.
► The O&M building provides accommodation for the operations personnel who
are responsible to ensure that the facility is operated in accordance with North American Electric Reliability Corporation (NERC) standards
18
he roJec
- 24/7 ro
he ene a le eratI0 r Ce e
ya
DA y
I a
e e
11 b
a
a1 e a
- r
- ca y fr
he 0 by 12 ech 1c1a
ec
1c an 1te
a a
I
e ma a g e r
>
u er
I
- ry
C
- rol an
a a c u1 1
10n ( C D
y te co lee ea m e a a ro n f r a d b a
1 n
a fee nf r at10
- o ro ler I ca ed
1 n
he rb ne a d b
- >
- n ro
r ma e auto
a t 1 c
a
J
ent ba ed on
e t point e tab/1 hed for the
a e re 1a le an
- e a on of
e 1te
►
T pr e accom o a 10
- he opera 10
are re po e e tha t a
1 1 1
y
I
- pera e
~
' O NEXTera
~
ENERGY~
Decommissioning overview
► CRW is responsible for decommissioning of the project and all costs associated
with decommissioning associated facilities
» Removal of 130 wind turbines and all existing above ground facilities » Remove roads and staging areas not desired by land owners to remain in place » Restore property or properties to pre-construction conditions including:
› Vegetation, drainage and other environmental features
» Repair county roads impacted by movement of heavy vehicles and frequent vehicle trips
19
►
C
1 re p
e eco 1 1on1 g o
e
p r
- J
e c a d al co t a o a ed ec a
- c1a e fac1 1 e
))
e o al of 130 n t rb e a d a l e tin abo e grou fac tI n a ea
- de r
y la
- e
to
e
a n pl ce
>
e tore p pe y or p o e Ie pre o true on c n It o
I
c u
I
g
>
Vege a 10
dra1 age a d ot er environ e a ea ure
>>
e a r o nty roa
I
a e by mo e e
- hea y e I le a d fre uent
veh c trI
NEXTera
~
ENERGY~
wind data analysis; landowner
- utreach
Crowned Ridge Projects Timeline
2006
PPA Executed
March 2017
Local Permitting Begins
June 2018
Wind Farm Design
Dec 2018
State Permitting Begins
Jan 2019
Material Procurement
Feb 2019
Construction Begins
Aug 2019
In Service Operations
Dec 2019
Contact information
Crowned Ridge Wind, LLC
Tyler Wilhelm Project Manager Tyler.Wilhelm@NextEraEnergy.com
South Dakota PUC Website
https://puc.sd.gov
21
Tyler Wilhelm
Pro1ect Manager
T I r W1lh Im htt m