Dennis Reed September 17, 2012
1
Dennis Reed September 17, 2012 1 To provide an overview of the - - PowerPoint PPT Presentation
Dennis Reed September 17, 2012 1 To provide an overview of the October/November Compliance filing The general layout of the proposed Tariff language Solicit input from various Working Groups Input must be received by the RTWG
1
2
3
4
Host TO builds and NTC(s) issued as needed
Is NTCC Needed ?
5
Y N
6
Transmission Service Generation Interconnect ITP Customer Signs Agreement Customer Signs Agreement BOD Approves Projects
All Projects Published in STEP
NTC (s) issues as needed (ROFR) Host TO builds and NTC(s) issued as needed (ROFR)
NTC issued
Is NTCC Needed ?
NTCC issued
Does the Project meet criteria? TO(s) Selected using current process (ROFR) TO Selection Process
Y Y N N
7
Sponsored Projects Sponsor Agrees to pay
Project Tracking
Cost OK? Review Project- Still proceed?
Cancel Project
Y Y N N
Sections I Sections I and II and II Opening and general information Sectio Section V n V STEP Report and approval / endorsement of projects Remaining Sections Remaining Sections VII VII to XI to XI
8
Sectio Section III n III ITP Planning Sectio Section III.8 (b) n III.8 (b) Detailed Project Proposal ** NEW ** ** NEW ** Sectio Section IV n IV Other Planning Processes Sectio Section VI n VI Construction of Transmission Facilities (Parts moved to Attachment Y)
Transmission Owner Designation Process
Section ction I I: Ov Overview erview Describes the subsequent Sections of the Attachments Defines which projects go through TO Selection Process in Section III All other projects go through Incumbent TO process Section IV Sec Section II: Defi n II: Defini nitions Section ction I III: II: T TO Selection lection Pr Proc
ss for Competitiv etitive U e Upgr grades ades Qualification Process Selection Process/RFP/Scoring
Proposal) Selected DTO can not assign project Default by DTO Sec Section n IV: Incum IV: Incumbent TO TO Sel Selection n Process Process Basically, current Attachment O, Section VI.6 language. Maintains ability of TO to assign a project Sect Sectio ion V: n V: Notifi Notificat cation to to Construct Construct Basically the same as in current Tariff, Attachment O, Section VI.6 All entities being assigned a project through either Section III or Section IV will get an NTC Defines an NTC for a cost estimate Sec Section VI: n VI: Projec Project Track t Tracking ng Process Process All projects are tracked by the TP Project costs changes are reported ITP Upgrad ITP Upgrades GI Upgrad GI Upgrades es When neede When needed QRP can QRP can get get Inc Incent ntive points points For DPP For DPP Spons Sponsored red Upgr Upgrades es Wh When n en needed eeded Meets c s condition ition Does not Does not Meet Meet cond condition Selected Selected entity entity gets gets An NTC An NTC
9
10
11
12
13
14
15
Generally tried to maintain current Tariff language
Any project where the TO is selected through either
Defined that an NTC may be issued for SPP to get a
16
17
18
19
To Qualify for Incentive points as part of the TO selection
A DPP project must be submitted during a 30 day window
If a DPP is approved, the stakeholder(s) which submitted
20
21
22
23
24