February 2012 DAWEI Sea Port Project DAWEI PROJECT DAWEI AND THE REGION PROJECT LOCATION Kunming India Middle East / Europe Dawei Africa Asia Regional Hub DAWEI Sea Port Project DAWEI PROJECT DAWEI PROJECT OVERVIEW PROJECT OVERVIEW AND


slide-1
SLIDE 1

February 2012

slide-2
SLIDE 2

DAWEI Sea Port Project

DAWEI AND THE REGION

DAWEI PROJECT

slide-3
SLIDE 3
slide-4
SLIDE 4

Asia Regional Hub

Africa Middle East / Europe

Dawei

Kunming

India

PROJECT LOCATION

slide-5
SLIDE 5

DAWEI Sea Port Project

DAWEI PROJECT OVERVIEW

DAWEI PROJECT

slide-6
SLIDE 6

G-to-G MOU signed on May 19th 2008 MOU signed between ITD and Myanma Port Authority, Ministry of Transport on June 12th 2008 Framework Agreement signed between ITD and Myanma Port Authority, Ministry of Transport on November 2nd 2010 for the development of the Dawei Deep Sea Port, Industrial

Estate, and Road and Rail Link to Thailand on a BOT basis.  Project established as a Special Economic Zone (SEZ)  Concession Period: 60 Years + Possible Extension  Land Lease Period: up to 75 Years  ITD granted concessions to develop the following projects:

  • Deep Sea Port
  • Industrial estate incl. heavy industries such as:

steel mill, oil refinery, petrochemical complex, fertilizer plant, power plant, and other utility services

  • Cross border road and rail link with connecting

transmission lines

  • Township for residential and commercial development

PROJECT OVERVIEW AND FRAMEWORK AGREEMENT

slide-7
SLIDE 7

Dawei Special Economic Zone Law enacted by the Myanmar Government on 27th January 2011 Government

Management Committee

  • f Dawei Special Economic Zone
  • Gov. departments

& organizations

  • Chairman
  • Vice Chairman
  • Secretary
  • Joint-Secretary

President Ministry of the Office of the President

  • Minister
  • Gov. of Tanintharyi

Region

  • representative(s)

Supporting Working Body

  • f Dawei Special Economic Zone

Relevant Gov. departments & Organizations Developer or Investor

  • representative(s)
  • representative(s)

Central Body

Central Working Body

The Central Working Body established on 28th April 2011 by the Myanmar Government. The Minister of National Planning and Economic Development as the Chairman. The Committee comprises of 15 other Deputy Ministers and Director Generals from various Ministries.

DAWEI SPECIAL ECONOMIC ZONE STRUCTURE

slide-8
SLIDE 8

Project Area defined as the Dawei Special Economic Zone

Industries and businesses in DSEZ shall be granted the protection and special privileges as follow:

 No Nationalization  The right to own land for development of industries and businesses  The right to import raw materials for processing and export without import duties and corporate income tax exemption  Production for domestic consumption subjected to normal tax rate  The right to import foreign management and skilled labor  Allowance for financial transactions required for normal business operation  Facilitate immigration and work permit  Facilitate company and business registration, permits, and licenses in ONE-STOP-SERVICE

LEGAL FRAMEWORK OF DSEZ LAW

slide-9
SLIDE 9

TAX EXEMPTION (proceeds of overseas sale)  Year 1-5 0%  Year 6-10 15%  Year 11-15 15% ; if profit is reinvested, otherwise 30% Possible extension of the tax exemption After the Tax Exemption period, income tax relief for that year may be applied for; depends on the VALUE OF EXPORT ITEMS are met according to the below conditions: Large Scale Investment: > 50% of total value of product Medium Scale Investment: > 60% of total value of product Small Scale Investment: > 70% of total value of product EXEMPTION OF COMMERCIAL TAX & VAT Export items EXEMPTION OF IMPORT TAX & CUSTOM DUTIES FOR RAW MATERIALS AND MACHINERIES Export-oriented processing business  0% for 5 years  50% reduction for the next 5years LAND USE  Large Scale Investment: up to 75 years  Medium Scale Investment: up to 60 years  Small Scale Investment: up to 40 years

DSEZ LAW INVESTMENT PROMOTION

slide-10
SLIDE 10

DAWEI Sea Port Project

PROJECT INVESTIGATION

DAWEI PROJECT

slide-11
SLIDE 11

Good Location for Port Development

  • Natural water depth able to

accommodate large-size vessels.

  • Natural shelter good for

anchorage.

  • No physical underwater & sub-

soil obstructions for approach channel & port basins.

  • Sufficient flat hinterland for

Industrial Estate in order to support / create throughput for the PORT.

  • Economical transportation for the

Road and Rail Links between DAWEI Port and Thailand.

  • Sufficient supply of local

construction material.

Dawei Deep Sea Port and Industrial Estate will cover an area of 250 km2 or 61,775 acres. The Dawei Project will demand sufficient land area to prevent industrial congestion, environmental problems and for future project expansion will altogether promote the well-being and livelihood of the community.

ITD INVESTIGATION – SITE SELECTION

slide-12
SLIDE 12

DAWEI Sea Port Project

PROJECT DEVELOPMENT PLAN

DAWEI PROJECT

slide-13
SLIDE 13

 Establishment of Dawei Development Company Limited in Myanmar to implement the Dawei Project.  Development of Basic Infrastructure:

  • Port
  • Road and Rail Link
  • Water Supply and Treatment System
  • Electricity
  • Telecommunication
  • Township

 Hired reputable consultants for detailed design study for port and road link.  Upon approval by the Myanmar Government, Port (1st Phase) and Road Link will begin construction by early 2012 and expect to complete within 4 years.  LAND AVAILABLE FOR IMMEDIATE RESERVATION BY INVESTORS.

PROJECT DEVELOPMENT PLAN

slide-14
SLIDE 14

 Appointed reputable consultants to conduct detailed design study

  • Port:
  • Road: EPSILON; TESCO; MINDWAY

Port: Servicing liquid cargo, agricultural products, general cargo, containers, and bulk cargo Road Link: 4-Lane Toll Highway with expansion to 8 lanes in later phase Temporary Jetty: NOW available for use. Access Road (Dawei – Phu Nam Ron): 160 Kilometer. Completed.

DEEP SEA PORT and ROAD LINK TO THAILAND

BASIC INFRASTRUCTURE PREPARATION

slide-15
SLIDE 15

DAWEI PROJECT ACCESS ROAD

slide-16
SLIDE 16

Corridor Link to Thailand

  • Roads
  • Railways
  • Transmission Lines
  • Oil & Gas Pipelines

200 m. CORRIDOR LINK TO THAILAND

slide-17
SLIDE 17

RESERVOIR AND WATER SUPPLY

slide-18
SLIDE 18

 Coal-Fired Power Plant: Land available for power plant development to serve Dawei Industrial Estate Plot location next to Bulk Port Development of an initial 400 MW to supply electricity during the Dawei Project construction period  Increase capacity to match future electricity demand in the industrial estate. Possibility to develop power plant to sell to EGAT and within the Industrial Estate under a long-term contract (PPA)  Proposal of 3,600 MW Sale to Thailand under consideration by EGAT and to conclude Tariff MOU.  Hydro Power Plant Tanintharyi Hydro Power Development up to 670 MW to serve the Dawei Industrial Estate.

POWER DEVELOPMENT PLAN

slide-19
SLIDE 19

DAWEI Sea Port Project

PROJECT LAYOUT

DAWEI PROJECT

slide-20
SLIDE 20

PROJECT LAYOUT

slide-21
SLIDE 21

DAWEI Sea Port Project

DAWEI DEEP SEA PORT

DAWEI PROJECT

slide-22
SLIDE 22

DAWEI DEEP SEA PORT

slide-23
SLIDE 23

DAWEI Sea Port Project

DAWEI ROAD LINK

DAWEI PROJECT

slide-24
SLIDE 24
slide-25
SLIDE 25

DAWEI Sea Port Project

TOWNSHIP DEVELOPMENT

DAWEI PROJECT

slide-26
SLIDE 26

DAWEI Sea Port Project LOCAL TOWNSHIP

Tha Pyae Zoon

(169 households)

Kya Khat Tabin-in

(331 households)

slide-27
SLIDE 27

DAWEI Sea Port Project DAWEI EXPATRIATE TOWNSHIP

slide-28
SLIDE 28

DAWEI Sea Port Project

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

DAWEI PROJECT

slide-29
SLIDE 29

ENVIRONMENTAL AND SOCIAL DEVELOPMENT

slide-30
SLIDE 30

DAWEI Sea Port Project

BUSINESS OPPORTUNITY FOR INVESTORS

DAWEI PROJECT

slide-31
SLIDE 31

DAWEI PROJECT INVESTMENT STRUCTURE

Strategic Level Partners

Township Port Coal-Fired Power Plant World Class Holiday Resort Industrial Estate Integrated Steel Mills Railway Toll Road Petrochemical Complex Refinery & Gas Complex Fertilizer Plants Utility Services Water Shipyards Tele- communication Logistics Chemical Complex Pulp & Paper

slide-32
SLIDE 32

DAWEI Sea Port Project

WORK PROGRESS AND PHOTOS

DAWEI PROJECT

slide-33
SLIDE 33

SITE PHOTO

slide-34
SLIDE 34

SITE PHOTO

slide-35
SLIDE 35

SOIL BORING

slide-36
SLIDE 36

ROAD LINK SURVEY AND CLEARING

slide-37
SLIDE 37

Auditorium Exhibition Hall Pavilion Villas

VISITOR CENTER

slide-38
SLIDE 38

ITD Camp ITD Camp Local Road in DSEZ Local Road in DSEZ

ITD CAMP AND LOCAL ROAD IN DSEZ

slide-39
SLIDE 39

TEMPORARY BRIDGE CROSSING DAWEI RIVER

slide-40
SLIDE 40

Thank You

“An Industrial Project That Could Change Myanmar”