Federal Way Link Extension

Citizen Oversight Panel Briefing 05/16/19

slide-2
SLIDE 2

2

Subhead

  • Bullet
slide-3
SLIDE 3
slide-4
SLIDE 4
slide-5
SLIDE 5
slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

Design Build Procurement Process

  • Request for Qualifications
  • Statement of Qualifications
  • Request for Proposal to Shortlisted Teams
  • Proposals Evaluated by Sound Transit and 3rd parties
  • Negotiations w/ Highest Ranked Team
slide-8