Franconia Park Master Plan Revision PUBLIC COMMENT MEETING April 1, - - PowerPoint PPT Presentation

franconia park master plan revision
SMART_READER_LITE
LIVE PREVIEW

Franconia Park Master Plan Revision PUBLIC COMMENT MEETING April 1, - - PowerPoint PPT Presentation

Franconia Park Master Plan Revision PUBLIC COMMENT MEETING April 1, 2014 Tonights Agenda Introductions: Judy Pedersen, Public Information Officer, FCPA Remarks: Supervisor McKay, Lee District Ed Batten, Park Authority Board Member, Lee


slide-1
SLIDE 1

Franconia Park Master Plan Revision

PUBLIC COMMENT MEETING April 1, 2014

slide-2
SLIDE 2

Introductions: Judy Pedersen, Public Information Officer, FCPA Remarks: Supervisor McKay, Lee District Ed Batten, Park Authority Board Member, Lee District Presentation: Andy Galusha, Project Manager, Park Planning Branch, FCPA Public Comment: Moderated by Judy Pedersen

Tonight’s Agenda

slide-3
SLIDE 3

Enhance Citizen’s Quality of Life Through: Natural & Cultural Resource Stewardship Recreational Opportunities Quality Facilities & Services

Park Authority Mission

slide-4
SLIDE 4

12 - Member Board 23,300+ Acres of Parkland 421 Parks Accredited 3-Time Gold Medal Winner

Fast Facts about FCPA

slide-5
SLIDE 5

Written Report Park Purpose & Classification Existing Conditions & Constraints Visitor Experience Planned Park Uses and Facilities Design Concerns

Park Master Plans in General

slide-6
SLIDE 6

Written Report Park Purpose & Classification Existing Conditions & Constraints Visitor Experience Planned Park Uses and Facilities Design Concerns Conceptual Development Plan (CDP) Conceptual Site Layout General Location of Facilities General Location of Use Areas Not Engineered Site Plan

Park Master Plans in General

slide-7
SLIDE 7

July 2013 Public Info Meeting Develop Draft Master Plan April 1 2014 Public Comment Meeting Draft MP Revisions Present Draft MP to PAB Summer 2014 30-Day Public Comment Period PAB Approval PUBLIC INPUT IS A KEY ELEMENT OF THE MASTER PLAN PROCESS

Park Master Plan Time Line

Tonight’s Meeting Conduct Site Research

slide-8
SLIDE 8

Staff Resources

Site Staff Archaeologists Landscape Architects Planners Natural Resource Specialists Operational Specialists Recreation Specialists Park Development Specialists

slide-9
SLIDE 9

Park Classification System

District Park Diverse experiences & activities Larger number of facilities Lighted facilities Longer hours & more users Visit of half day + 50 + Acres Serve 3 to 6 miles

slide-10
SLIDE 10

Location of Franconia Park

I-495 I-95 Franconia Road Thomas Drive Bowie Drive Willowfield Way Bowie Drive Thomas Drive

slide-11
SLIDE 11

Nearby Parks

Backlick Stream Valley Lee High Monticello Woods Trailside Monticello Woods Lee High Trailside

slide-12
SLIDE 12

Site History

Early History: Native American

slide-13
SLIDE 13

Site History

Early History: Native American 1800s: Farmland

slide-14
SLIDE 14

Site History

Early History: Native American 1800s: Farmland 1937: Farming Ceased

slide-15
SLIDE 15

Site History

Early History: Native American 1800s: Farmland 1937: Farming Ceased Early 50s

slide-16
SLIDE 16

Site History

Early History: Native American 1800s: Farmland 1937: Farming Ceased Late 50s – 60s: Beltway Staging Gravel Pit

slide-17
SLIDE 17

Site History

Early History: Native American 1800s: Farmland 1937: Farming Ceased Late 50s – 60s: Beltway Staging 1970s: Park Authority Acquired

slide-18
SLIDE 18

Site History

Early History: Native American 1800s: Farmland 1937: Farming Ceased Late 50s – 60s: Beltway Staging 1970s: Park Authority Acquired Master Planned Constructed

slide-19
SLIDE 19

Park Use

Ball Fields

slide-20
SLIDE 20

Park Use

Ball Fields Garden Plots

slide-21
SLIDE 21

Park Use

Ball Fields Garden Plots Trails

slide-22
SLIDE 22

Park Use

Ball Fields Garden Plots Trails Parking

slide-23
SLIDE 23

Park Use

Ball Fields Garden Plots Trails Parking Wooded

slide-24
SLIDE 24

Park Use

Ball Fields Garden Plots Trails Parking Wooded Wildlife

slide-25
SLIDE 25

Existing Conditions

Topography

slide-26
SLIDE 26

Existing Conditions

Topography Steep Slopes

slide-27
SLIDE 27

Existing Conditions

Topography Steep Slopes Hydrology

slide-28
SLIDE 28

Existing Conditions

Topography Steep Slopes Hydrology Resource Protection

slide-29
SLIDE 29

Existing Conditions

Topography Steep Slopes Hydrology Resource Protection Vehicle Access

P P

slide-30
SLIDE 30

Existing Conditions

Topography Steep Slopes Hydrology Resource Protection Vehicle Access Pedestrian Access

P P

slide-31
SLIDE 31

Existing Conditions

Topography Steep Slopes Hydrology Resource Protection Vehicle Access Pedestrian Access Existing Facilities

slide-32
SLIDE 32

Master Planned - Unbuilt Facilities

Additional Parking

slide-33
SLIDE 33

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts

slide-34
SLIDE 34

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts

slide-35
SLIDE 35

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery

slide-36
SLIDE 36

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building

slide-37
SLIDE 37

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard

slide-38
SLIDE 38

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes

slide-39
SLIDE 39

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts

slide-40
SLIDE 40

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts Tot Lot & Playground

slide-41
SLIDE 41

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts Tot Lot & Playground Picnic Area

slide-42
SLIDE 42

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts Tot Lot & Playground Picnic Area Sled Run

slide-43
SLIDE 43

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts Tot Lot & Playground Picnic Area Sled Run Lighted Diamond Fields

slide-44
SLIDE 44

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts Tot Lot & Playground Picnic Area Sled Run Lighted Diamond Fields Overlay Rectangle

slide-45
SLIDE 45

Master Planned - Unbuilt Facilities

Additional Parking Tennis Courts Tennis Practice Courts Archery Concession Building Shuffleboard Horseshoes Multiuse Courts Tot Lot & Playground Picnic Area Sled Run Lighted Diamond Fields Overlay Rectangle Loop Trail

slide-46
SLIDE 46

Address in the Master Plan Revision

Park and Recreation Needs Expand Existing Features Field Capacity Garden Plots Nursery Parking & Circulation Protect Natural Areas Permanent Restroom Support Facilities Add New Facilities Dog Park Playground Trails Connectivity

slide-47
SLIDE 47

Master Plan Revision

Planned Features Removed Upgrade Retained Features New Features

slide-48
SLIDE 48

What Will Be Removed from 1974 Plan

Tennis Courts

slide-49
SLIDE 49

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts

slide-50
SLIDE 50

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building

slide-51
SLIDE 51

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building Shuffleboard

slide-52
SLIDE 52

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building Shuffleboard Horseshoes

slide-53
SLIDE 53

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building Shuffleboard Horseshoes Multiuse Courts

slide-54
SLIDE 54

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building Shuffleboard Horseshoes Multiuse Courts Sled Run

slide-55
SLIDE 55

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building Shuffleboard Horseshoes Multiuse Courts Sled Run Diamond Fields

slide-56
SLIDE 56

What Will Be Removed from 1974 Plan

Tennis Courts Tennis Practice Courts Concession Building Shuffleboard Horseshoes Multiuse Courts Sled Run Diamond Fields Overlay Rectangle

slide-57
SLIDE 57

What Will Remain The Same

Park Rules

slide-58
SLIDE 58

What Will Remain The Same

Park Rules Resource Protection

slide-59
SLIDE 59

What Will Remain The Same

Park Rules Resource Protection Visitor Access

P P

slide-60
SLIDE 60

What Will Remain The Same

Park Rules Resource Protection Visitor Access Existing Facilities

P P

slide-61
SLIDE 61

What Will Remain The Same

Park Rules Resource Protection Visitor Access Existing Facilities District Park Status

P P

slide-62
SLIDE 62

Rectangle Field

Conceptual Development Plan – Features Retained

slide-63
SLIDE 63

Conceptual Development Plan – Features Retained

Rectangle Field Playground

slide-64
SLIDE 64

Rectangle Field Playground Picnic Area

Conceptual Development Plan – Features Retained

slide-65
SLIDE 65

Rectangle Field Playground Picnic Area Open Play Area

Conceptual Development Plan – Features Retained

slide-66
SLIDE 66

Rectangle Field Playground Picnic Area Open Play Area Loop Trail

Conceptual Development Plan – Features Retained

slide-67
SLIDE 67

Rectangle Field Playground Picnic Area Open Play Area Loop Trail Expanded Parking

Conceptual Development Plan – Features Retained

slide-68
SLIDE 68

Rectangle Field Playground Picnic Area Open Play Area Loop Trail Expanded Parking Resource Protection

Conceptual Development Plan – Features Retained

slide-69
SLIDE 69

Conceptual Development Plan – Upgrades

Existing Fields

slide-70
SLIDE 70

Newest Lighting Technology Address Light Trespass Full Cut Off Shields Web Based Controls

Conceptual Development Plan – Upgrades

slide-71
SLIDE 71

Conceptual Development Plan – Upgrades

Existing Fields Garden Plots

slide-72
SLIDE 72

Conceptual Development Plan – Upgrades

Existing Fields Garden Plots Plant Nursery

slide-73
SLIDE 73

Conceptual Development Plan – Upgrades

Existing Fields Garden Plots Plant Nursery Parking Areas

slide-74
SLIDE 74

Conceptual Development Plan – New Features

Off Leash Dog Area

slide-75
SLIDE 75

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations

slide-76
SLIDE 76

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations Skate Spot

slide-77
SLIDE 77

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations Skate Spot Overlook

slide-78
SLIDE 78

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations Skate Spot Overlook Vendor Pad

slide-79
SLIDE 79

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations Skate Spot Overlook Vendor Pad Flex Program Space

slide-80
SLIDE 80

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations Skate Spot Overlook Vendor Pad Flex Program Space Pedestrian Entrance

slide-81
SLIDE 81

Conceptual Development Plan – New Features

Off Leash Dog Area Fitness Stations Skate Spot Overlook Vendor Pad Flex Program Space Pedestrian Entrance Revegetation

slide-82
SLIDE 82

Pedestrian Connectivity to Nearby Parks

Franconia Monticello Woods Trailside Trail Monticello Woods Trailside Franconia

slide-83
SLIDE 83

Next Steps in Planning Process

30 Day Comment Period Revise Plan as needed Present to Park Authority Board For Action - Summer

slide-84
SLIDE 84

Help Plan Your Park

Please visit our website: http://www.fairfaxcounty.gov/parks/plandev/franconia.htm Please send comments to: By e-mail: parkmail@fairfaxcounty.gov Old Fashioned Snail Mail: Andy Galusha, Project Manager Planning & Development Division, FCPA 12055 Government Center Parkway, Suite 406 Fairfax, Virginia 22035 Or By Phone: Phone: 703-324-8702