HOLDER WRIGHT PARK UPDATED PLAN PRESENTATION AUGUST, 25 2016 - PowerPoint PPT Presentation
HOLDER WRIGHT PARK UPDATED PLAN PRESENTATION AUGUST, 25 2016 HOLDER WRIGHT PARK - INTRODUCTION VICINITY MAP One mile northeast of the historic district center. Scioto River is just to the west. Scenic Wrights Run Creek runs
HOLDER WRIGHT PARK UPDATED PLAN PRESENTATION AUGUST, 25 2016
HOLDER WRIGHT PARK - INTRODUCTION
VICINITY MAP • One mile northeast of the historic district center. • Scioto River is just to the west. • Scenic Wright’s Run Creek runs through the site. • Site will be accessible from the Emerald Parkway side of the property.
AERIAL IMAGE OF PROPERTY
MASTER PLAN STUDY AREA • Historic earthworks site encompass three properties totaling 47.1 acres. • 21.4 acres owned by City of Dublin is on the eastern side of study area. • Remaining 25.6 acres are privately owned. • Preservation of the historic earthworks and farm house, while providing an educational and passive recreational space was identified as a priority for the site.
EARTHWORKS AND NATURAL SURROUNDINGS • Earthworks were farmed over the years – making some difficult to see. • Earthworks will be highlighted with vegetation for visibility. • Wright’s Creek will have selective clearing done to open up views to the scenic channel.
HISTORIC FARM HOUSE • Believed to be the first framed house in the area (others being log cabins). • Restored structure will be used for an interpretive center. • Archeological artifacts from site displayed.
ARCHAEOLOGICAL DISCOVERY • Archaeological excavations were done to preserve any artifacts within construction areas (OSU Field Research Site). • Jr. Archaeological discovery programs. • Educational tour programs.
HOLDER WRIGHT PARK – MASTER PLAN CONCEPT
HOLDER WRIGHT PARK – MASTER PLAN CONCEPT
HOLDER WRIGHT PARK – MASTER PLAN CONCEPT
PARK PLANS AND CONSTRUCTION
CONSTRUCTION PHASING PLAN • Phase 1 & 2: Construction will be the Visitor Orientation Space (red line) and Interpretive Center (blue line). • Entry Drive & Parking Lot, Visitor Orientation Center, Restrooms, Small Pedestrian Bridge, and Trail to Visitor Orientation Center (Farm House). • Phases 3-5: To be completed in the future as Capital Improvement Project Funding is allocated.
HOLDER WRIGHT PARK – SITE PLAN
HOLDER WRIGHT PARK – RESTROOM BUILDING
HAPPENING AROUND DUBLIN • Corporate Area Plan Public Meeting • Metro, Blazer, & Emerald business districts, & Frantz Rd corridor • Weds, Aug. 31, 6:30 p.m. • IGS Energy Community Room • Homeowners Association Meeting • Weds, Oct. 19 • Bridge Park hard hat tour • Every Thurs. • BridgeStreet.DublinOhioUSA.gov to sign up