I-35E Phase 2 Project April 30, 2020

I-35E Phase 2 Project

Texas Transportation Commission

April 30, 2020

slide-2
SLIDE 2

I-35E Phase 2 Project April 30, 2020

Minute Order authorization

2

Sum ummary o y of Commission A n Acti tion:

  • Authorize TxDOT to issue a request for qualifications (RFQ) to design,

construct and potentially maintain the I-35E Phase 2 Project in the Dallas District from I-635 to the Denton County Line.

slide-3
SLIDE 3

I-35E Phase 2 Project April 30, 2020

Purpose

3

  • Top 100 ranking:
  • Direct - 60
  • Indirect – 15, 57
  • Project limits: I-635 to the Denton

County line

  • Project purpose:

– Improve safety and mobility – Relieve congestion – Reduce travel time – Accommodate projected growth through the region

slide-4
SLIDE 4

I-35E Phase 2 Project April 30, 2020

Overview

4

PRESENT CONDITION PROPOSED CONSTRUCTION

  • Texas Clear Lanes Project
  • Total length: 6.39 miles
  • Project Scope:

– Reconstruct and widen general purpose lanes from 6 to 8 lanes – Reconstruct “grandfathered” existing 2 reversible tolled managed lanes (no increase in capacity) – Reconstruct continuous frontage roads – Numerous intersection improvements

  • Design-build cost estimate: $600M

Added capacity shown with purple arrows

slide-5
SLIDE 5

I-35E Phase 2 Project April 30, 2020

Alternative delivery support tool

5

  • Decision support tool

– Used to determine best delivery method:

  • Design-bid-build
  • Design-build

– Tool considers TxDOT’s goals and specific project characteristics.

  • Results

– Tool indicates design-build as most appropriate delivery method with a score

  • f 0.48 (scale of -1.00 to 1.00).
slide-6
SLIDE 6

I-35E Phase 2 Project April 30, 2020

Design-build anticipated timeline

6

Milestone Date Commission action to issue RFQ April 30, 2020 Issue RFQ May 2020 Qualification statements due June 2020 Commission action to issue RFP Summer 2020 Issue final RFP Fall 2020 Proposals due Spring 2021 Commission action for conditional award Spring 2021 Contract execution Summer 2021 Construction completion Late 2025/Early 2026