MEASURE L BOND UPDATE January 14, 2020 Measure L Overview - PDF document
MEASURE L BOND UPDATE January 14, 2020 Measure L Overview Project Updates Program Schedule Review Measure L Project Updates Cherrywood Elementary School - FIS In progress: Replacement of folding door Complete:
MEASURE L BOND UPDATE January 14, 2020
Measure L – Overview • Project Updates • Program Schedule Review
Measure L – Project Updates Cherrywood Elementary School - FIS • In progress: • Replacement of folding door • Complete: • Elevator – Passed State Inspection on December 19, 2019
Measure L – Project Updates Cherrywood FIS - Before
Measure L – Project Updates Cherrywood FIS – After
Measure L – Project Updates Cherrywood FIS - Before
Measure L – Project Updates Cherrywood FIS - After
Measure L – Project Updates Cherrywood FIS - After
Measure L – Project Updates Cherrywood FIS – Before
Measure L – Project Updates Cherrywood FIS - After
Measure L – Project Updates Cherrywood FIS - Before
Measure L – Project Updates Cherrywood FIS - After
Measure L – Project Updates Additional Projects • Complete: • Wireless thermostat's at portables • Concrete Benches at Piedmont • Tack board at Toyon Library • In Construction: • Traffic Gates - Phase 2 – NB and SM • Toyon - MPR Wall Infill
Measure L – Project Updates Additional Projects • Bidding: • Traffic Gates - Phase 2 – PM • Perimeter Fencing • Laneview • Library Shelving • Music Room Furniture • Noble FIS - Mural • Vinci Park – FIS Canopy • Design: • Perimeter Fencing • Noble • Ruskin • Sierramont
Measure L – Project Updates Additional Projects • Design: • Morrill – HVAC • Toyon - HVAC • Paving – Laneview Staff Parking Lot • Main Alarm Security Alarm Panels • Security Camera @ Middle Schools • Lunch Shade Structures • Noble • Ruskin • Morrill • Piedmont • Entry Canopy • Marquee • Lunch Shade Structure
Measure L – Program Schedule Construction Legend Furniture Legend Design Preconstruction Furniture Design Lead Tim e DSA Review Construction Quote Pricing Furniture Received and Placed Bid Start of School PO Generated Award Punch List CONSTRUCTI ON PROJECTS 2 0 2 0 January February March April May June July August September Week Week Week Week Week Week Week Week Week 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5 CHERRYWOOD FIS/ MODERNIZATION NOBLE FIS MURAL PI EDMONT ENTRY CANOPY MARQUEE BENCH INSTALLATION AND CONCRETE WORK LUNCH SHADE STRUCTURE TOYON MPR Wall Infill VI NCI PARK FIS CANOPY TRAFFI C GATES NB & SM PM HVAC PROJECTS TOYON MORRILL PERI METER FENCI NG LANEVIEW NOBLE RUSKIN SIERRAMONT
Measure L – Program Schedule Construction Legend Furniture Legend Design Preconstruction Furniture Design Lead Tim e DSA Review Construction Quote Pricing Furniture Received and Placed Bid Start of School PO Generated Award Punch List CONSTRUCTI ON PROJECTS 2 0 2 0 January February March April May June July August September Week Week Week Week Week Week Week Week Week 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 1 2 3 4 5 1 2 3 4 1 2 3 4 5 PAVI NG - LANEVI EW STAFF PARKI NG LI OT MAI N ALARM SECURI TY PANEL REPLACEMENT SECURI TY CAMERAS MI DDLE SCHOOLS LUNCH SHADE STRUCTURES NOBLE RUSKIN MORRILL FURNI TURES PROJECTS LIBRARY SHELVING MUSIC ROOM FURNITURE