News: 1. Update on WBS 2. WBS next steps 3. Instrumentation FT - - PowerPoint PPT Presentation

News: 1. Update on WBS 2. WBS next steps 3. Instrumentation FT status Sowjanya Gollapinni (UTK) Anselmo Cervera Villanueva (IFIC) Joint SP/DP CISC meeting October 27, 2017 Updated WBS We are version v4 for our WBS. Latest version


slide-1
SLIDE 1

News:

  • 1. Update on WBS
  • 2. WBS next steps
  • 3. Instrumentation FT status

Sowjanya Gollapinni (UTK) Anselmo Cervera Villanueva (IFIC)

Joint SP/DP CISC meeting October 27, 2017

slide-2
SLIDE 2

2

Updated WBS

  • We are version “v4” for our WBS. Latest version “v4a”. Please use

the latest version.

– https://docs.dunescience.org/cgi-bin/private/ShowDocument?docid=5609

  • Separate WBS files for SP and DP

– This is the recommendation from the project office – We are a joint consortium and we will conduct our activities as

  • such. The SP/DP separation is only for WBS as it makes things

easier from the project side with e.g. costing.

– In our case, SP is the first detector and DP is the second detector – Common SP/DP activities that occur only once are included

under SP (see next slide)

slide-3
SLIDE 3

3

Common Items

Items common to both SP and DP are only included once in SP. In SP WBS, these items have “Common to DP” in their felds in orange.

slide-4
SLIDE 4

4

WBS Levels – L0, L1, L3

  • L0

–

SP

–

DP

  • L1

–

APA

–

SP-ELE

–

SP-PDS

–

CRP

–

DP-ELE

–

DP-PDS

–

HVS

–

DAQ

–

SC/CI

–

TC

  • L2

–

Management (includes reviews & milestones)

–

Physics & Simulations

–

Design, Engineering and R&D (includes subsystem test facilities & QA)

–

Production Setup (includes tooling)

–

Production (includes component production, assembly & testing)

–

Integration (contributions to activities at global integration facility)

–

Installation (contributions to activities at SURF)

  • L3

–

Cryogenic Instrumentation

–

Slow Controls

slide-5
SLIDE 5

5

WBS Levels – L4

  • L4

–

Purity Monitors

–

Thermometry (Dynamic & Static thermometers)

–

Cameras (cold & warm cameras, and light emitting system)

–

Gas Analyzers (with LBNF)

–

Liquid Level Monitoring System (with LBNF)

–

Cryogenic Internal Piping (with LBNF)

–

Slow Controls Hardware (including network & computing hardware)

–

Slow Controls Infrastructure

–

Slow Controls Software

–

Slow Controls Quantities

–

Local Integration

slide-6
SLIDE 6

6

WBS – immediate steps

At the RRB, we will show pie charts that attempt to summarize institutional interests within each consortia (e.g. Pie chart on the left for APA)

  • RRB meeting – November 2nd
  • Global WBS: The goal is merge all the WBS from all the consortia into a

global WBS document which will be presented at the RRB meeting

  • Institutional Interests: The next main step in the process is to attach

institutional interests to specific WBS items where appropriate

– It’s understood that not every WBS element will have an attached

institutional interest at this point in time

– Deadline: Tuesday, October 31st

slide-7
SLIDE 7

7

WBS – immediate steps

  • Please look at the latest WBS files and put your institution's name down

next to items you and your group plans to contribute

  • Any questions/concerns on the updated WBS or if something is not clear,

please write to myself and Anselmo. We can schedule a Zoom meeting as needed.

  • Can you meet the October 31st deadline to get this information to me and

Anselmo?

Questions/comments/thoughts?

slide-8
SLIDE 8

8

Other activities & Post-RRB (from Eric)

  • The WBS prepared represent activities that will happen in 2020 for the

construction effort of SP and DP

–

We also need to prepare a list of R&D activities in 2018/2019 for producing

  • TDRs. Soon we will need to provide feedback on this item.

Post-RRB

  • The next major milestone for the consortia will be completing the Technical

Proposal by April, 2018

  • Technical proposal will include

–

Written description of proposed subsystems and any alternatives under consideration

–

Updated WBS and associated list of institutional interests

–

Initial subsystem cost estimates

–

Initial draft of schedule for construction activities

slide-9
SLIDE 9

9

Instrumentation FT Status

  • Instrumentation Feedthroughs: Thermometers, Purity Monitors & Cameras
  • As a response to our request for ports, we were asked to explore the possibility
  • f using cable trays and bolts that are present at the top and bottom (all along

the height for the corners) of the cryostat.

– Purity Monitor folks (Andrew/Jianming) and Thermometer folks

(Jelena/Anselmo) have been exploring this

– Cable trays are in the corners and no FTs on top of them

slide-10
SLIDE 10

10

Instrumentation FT Status

  • First thing we are exploring by looking at

fluid flow simulations is if the fluid flow at the corners a good representation of what is going on in the rest of the cryostat.

  • For Purity Monitors: seems like the

corner location is not an issue from fluid flow side.

–

Also, not an issue in terms of mounting the device.

–

Near by ports and how we will route cables needs more exploration

  • For Thermometers: seems like corners

are not good representation of what goes

  • n in the rest of the cryostat

–

Mounting is also a challenge especially Dynamic T-gradient thermometers

–

Talk by Anselmo on this

ProtoDUNE