November 19, 2013 Glenbard South High School 4:30 PM to 7:30 PM

IL 53 and IL 56 Improvements

Project Limits Preferred Alternative Environmental Resources Land Acquisition Next Steps

slide-2
SLIDE 2

1/27/2016 2

IL 53 and IL 56 Improvements

DuPage County

DOWNERS GROVE GLEN ELLYN LOMBARD

IL 53 and IL 56 Improvements

slide-3
SLIDE 3

1/27/2016 3

IL 53 and IL 56 Improvements

Improves Roadway Safety Alleviates Roadway Flooding Enhances Lane Continuity Accommodates Capacity Demands Enhances Pedestrian and Bicyclist Facilities

IL 53 and IL 56 Improvements

Public Meeting – 2006 Noise and Drainage Forum ‐ 2007 Local Agency Coordination

Park Districts, Villages, Township, County, Morton Arboretum, Forest Preserve District, County Sheriff, Fire Departments

Working Groups and Agencies

Valley View / Butterfield East Associations Committee 53 Army Corps of Engineers FHWA Environmental Groups IDNR

slide-4
SLIDE 4

1/27/2016 4

IL 53 and IL 56 Improvements IL 53 and IL 56 Improvements

Looking East

slide-5
SLIDE 5

1/27/2016 5

IL 53 and IL 56 Improvements

Looking North

IL 53 and IL 56 Improvements

DuPage County

slide-6
SLIDE 6

1/27/2016 6

IL 53 and IL 56 Improvements IL 53 and IL 56 Improvements

slide-7
SLIDE 7

1/27/2016 7

IL 53 and IL 56 Improvements

Wetlands

Impacting 11 Wetland Sites Approximately 5.8 acres

Trees

Coordinate with FPD to Minimize Impacts Tree Replacement 1:1 According to IDOT Policy

IL 53 and IL 56 Improvements

Hidden Lake Forest Preserve

Section 4(f) Evaluation Approximately 6.3 Acres for Permanent or Temporary Easements No Impacts to Recreational Facilities

slide-8
SLIDE 8

1/27/2016 8

IL 53 and IL 56 Improvements IL 53 and IL 56 Improvements

Noise Wall Reasonable & Feasible Locations

slide-9
SLIDE 9

1/27/2016 9

IL 53 and IL 56 Improvements

Route 53 & Route 56 Intersection Route 53 Shifted Alignment Storm Water Detention and Water Quality Features

IL 53 and IL 56 Improvements

Fee Simple Acquisition of All Rights and Interest 10.34 Acres Permanent Easement Ownership Retained by Property Owner Maintenance Access 6.8 Acres Temporary Easement Ownership Retained by Property Owner Used for Grading During Construction Only 9.06 Acres

slide-10
SLIDE 10

1/27/2016 10

IL 53 and IL 56 Improvements

14 Residences in Floodplain Uniform Relocation Assistance and Real Estate Property Acquisition Act as Amended IDOT Land Acquisition Representatives Present Tonight

IL 53 and IL 56 Improvements

  • Preliminary

Engineering and Environmental Study

  • Design Approval Spring

2014

Phase I

  • Contract Plan

Preparation and Land Acquisition

  • 18 – 24 Months

Phase II

  • Construction
  • IL 56 (Funded*)
  • IL 53 (Unfunded)

Phase III

*Included in IDOT’s FY 2014‐2019 Multi‐Modal Transportation Improvement Program

slide-11
SLIDE 11

1/27/2016 11

IL 53 and IL 56 Improvements

Cost Estimate

IL 56 / IL 53 Intersection with IL 56 = $21,000,000 IL 53 = $12,000,000 Included in FY2014‐2019 Proposed Multi‐Modal Transportation Improvement Program Not in the Program

IL 53 and IL 56 Improvements

Ask Questions View Exhibits Provide Comments

Submit Tonight on a Comment Form Verbal Comments by Court Reporter Send Comments By Mail Submit Comments By Email to IL53‐56@transystems.com Due by December 11, 2013