Patrick Henry School and Recrea3on Center Advisory Group Meeting Thursday, July 7, 2016 6:00 PM www.acps.k12.va.us Mee3ng Agenda Project Update Plans Comments Floor Plans Site Plan / Exteriors Next Steps


slide-1
SLIDE 1

www.acps.k12.va.us

Patrick Henry School and Recrea3on Center

Advisory Group Meeting Thursday, July 7, 2016 6:00 PM

slide-2
SLIDE 2

www.acps.k12.va.us

2

Mee3ng Agenda

  • Project Update
  • Plans Comments
  • Floor Plans
  • Site Plan / Exteriors
  • Next Steps
slide-3
SLIDE 3

www.acps.k12.va.us

3

Project Schedule Overview - 2016

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Schematic Design Design Development Construction Documents Development Special Use Permit (DSUP) Process Concept I (3 Op9ons) – Basic site plan with building footprint, parking/ circula3on, open spaces and approximate square footage and height

  • Final Site Plan Op3on endorsed by School Board May 19, 2016

Concept II – Refine layout, square footage, building height and materials, early u3lity studies, final number of parking spaces and vehicle/delivery access Preliminary Site Plan – Building architecture, final u3lity designs, site ligh3ng, landscaping and site scape

Concept I Concept II Preliminary Site Plan Public Hearing + Council Hearing

SB Approval of Schematic Design

slide-4
SLIDE 4

www.acps.k12.va.us

4

Project Update

  • Concept II Submission made on June 24th
  • Selec3on of construc3on manager
  • Review of plans and systems with ACPS and RCPA
  • Mechanical, electrical, plumbing
  • AV, IT, and Security
  • Food service and custodial
  • Educational
slide-5
SLIDE 5

www.acps.k12.va.us

5

Project Update – June 15th Mee9ng

  • Natural materials for exterior
  • Details of black box theatre
  • Parking details
  • Outdoor green roof spaces
  • Access to DSUP submissions
  • Comments on floor plans and site plan

What We Heard

slide-6
SLIDE 6

www.acps.k12.va.us

6

Project Update – June 15th Mee9ng

  • Exterior of primarily brick and glass with metal panel accent
  • Mee3ngs with ACPS staff on black box theatre
  • Parking details under development
  • Green roof spaces being phased out by ACPS for safety and

maintenance reasons

  • Plans provided for comment tonight

What We’re Doing

slide-7
SLIDE 7

www.acps.k12.va.us

7

Project Update – Black Box Theatre

  • What is a Black Box Theatre?
  • A black box is a bare room with a movable seating area, a

movable stage, and a Ulexible lighting system.

  • Flexible use for instruc3on and performance
  • Music
  • Dance
  • Art display
  • Capacity of 75 – 150 spectators for in3mate performances
  • Allows for informal and formal performance
slide-8
SLIDE 8

www.acps.k12.va.us

8

Project Update – Black Box Theatre

slide-9
SLIDE 9

www.acps.k12.va.us

9

Plans Review - Discussion

  • General comments within confines of Site Specific

Program Document and Educa3onal Specifica3ons

  • Adjacencies
  • Opera3onal flow of facility

NOT TO INCLUDE

  • Changes in program use
  • Changes to sizes of spaces
slide-10
SLIDE 10

www.acps.k12.va.us

10

Plans Review – First Floor

slide-11
SLIDE 11

www.acps.k12.va.us

11

Plans Review – Second and Third Floors

slide-12
SLIDE 12

www.acps.k12.va.us

12

Plans Review – Site Plan

slide-13
SLIDE 13

www.acps.k12.va.us

13

Plans Review – Site Plan

slide-14
SLIDE 14

www.acps.k12.va.us

14

Plans Review – Site Plan

slide-15
SLIDE 15

www.acps.k12.va.us

15

Plans Review – Site Plan

slide-16
SLIDE 16

www.acps.k12.va.us

16

Plans Review – Development Areas

  • Access into Cafeteria from bus loop – revised loading for

kitchen area

  • Pedestrian access off N. Latham Street (steps, ramps)
  • Incorpora3on of DSUP Review Comments in July
slide-17
SLIDE 17

www.acps.k12.va.us

17

Next Steps – Advisory Group

  • Keep community informed of the project and processes
  • Keep project team informed of community’s views
  • Provide comment on construc3on logis3cs and planning to

maintain safe opera3ons of school and recrea3on center

  • Provide comment on general aspects such as exterior

eleva3ons The Advisory Group will be involved in the following ways un3l the end of their year term (December 2016):

slide-18
SLIDE 18

www.acps.k12.va.us

18

Next Steps – Project Team

  • Onboarding of Construc3on Manager for es3ma3ng and

constructability

  • Electronic project updates throughout the Summer
  • Board approval of schema3c design in August 2016
  • Advisory Group Mee3ng in August
  • DSUP Completeness Submission in late August
  • Community Mee3ngs resume in September
  • Con3nua3on of itera3ve design process

hPp://www.acps.k12.va.us/facili9es/ph/