Precast Concrete Segments for Bridges
Fabrication and Assembly - Fundamental Details Jacques COMBAULT Consultant & Technical Advisor Professor at the ENPC Vice-President of IABSE Jacques Combault, born in 1943, has been working as bridge designer for more than 30 years, with Campenon Bernard and GTM, both being now companies of VINCI (France). Recently involved in major projects abroad, he is currently Consultant and Technical advisor. SUMMARY For more than 40 years, the construction of large bridges has been marked by the association
- f intensive pre-fabrication of box-girders in match-cast sections and assembly of these
segments using powerful equipments, either movable launching gantries or temporary stay
- cables. Associated with modern, well designed prestressing systems combining both internal