Department of Community Assets and Development PROJECT 201, 2020 STREET REHABILITATION May 12, 2020 Public Hearing PROJECT 201 SCHEDULE Assessment Neighborhood Public Feasibility Award Public Hearing Informational Improvement
Neighborhood Informational Meeting February 27, 2020 Feasibility Study & Set Improvement Hearing Date March 10, 2020 Public Improvement Hearing CANCELLED March 24, 2020 Public Improvement Hearing May 12, 2020 Award Contract June 2020 Start Construction Summer 2020 Project Completion October 2020 Assessment Hearing September 2021
PROJECT 20‐1 SCHEDULE
PUBLIC HEARING MAILING
COMPREHENSIVE STREET PLAN
- City Council adopted plan for maintaining our
streets and alley system.
- New Brighton has about 64 miles of streets
and alleys.
- Streets are rehabilitated about every 25 to 30
years.
- Rehabilitate about 2.1 miles per year.
- Rehabilitate on a neighborhood basis to
minimize disruption.
STREET IMPROVEMENTS
- 0.86 miles of streets in project corridor
- Last rehabilitated in 1990
- Streets to be constructed to their original width
- Remove and replace bituminous pavement and base
material
- Replace broken and settled curb and gutter
- Pedestrian ramp ADA upgrades
WATER SYSTEM IMPROVEMENTS
- Watermain is C.I.P. with a low
break frequency; will not be replaced
- 10 hydrants will be replaced
based on age and no longer producing parts for repairs
STORM SEWER SYSTEM IMPROVEMENTS
- Replace 7 existing block‐built
structures with precast concrete structures
- Remove catch basin from
driveway (Eastman Dr/Robin Ln)
- Flex Seal 14 catch basins
- Replace existing grates on 6
catch basins
SANITARY SEWER SYSTEM IMPROVEMENTS
- Sewer mains televised. No issues
found requiring open cutting of street
- Flex Seal 16 manholes
ESTIMATED PROJECT COSTS IMPROVEMENT ESTIMATED COST Construction Costs $1,083,000 Contingency (10%) $108,300 Engineering & Administration (20%) $238,300 Soil Borings $6,800 Surveying Services $9,900 Legal & Fiscal (1%) $11,900 TOTAL ESTIMATED PROJECT COST $1,458,200
PROJECT FUNDING IMPROVEMENT CITY COST ASSESSABLE COST TOTALS Street Reconstruction
- 1. $721,000
- 2. $240,400
$961,400 Watermain Improvements $144,000 $0 $144,000 Sanitary Sewer Improvements $27,300 $0 $27,300 Storm Sewer Improvements $325,500 $0 $325,500 Total $1,217,800 $240,400 $1,458,200
- 1. 75 percent of Street Rehabilitation costs.
- 2. 25 percent of Street Rehabilitation costs.
ASSESSMENT CALCULATIONS Assessment Method: Per Lot Basis Valley View Lane = 29 Lots Knollwood Drive = 4 Lots Eastman Drive = 21 Lots Gregory Drive = 4 Lots Longview Drive = 14 Lots Robin Lane = 5 Lots City of New Brighton (Sunny Square Park) 273.98’ / 75’ (standard lot frontage) = 3.65 Lots Total Assessable Lots = 80.65 Preliminary Estimated Assessments 25 % of Anticipated Street Costs = $240,400 / 80.65 Lots = $2,980 Per Lot
EXAMPLE ASSESSMENT PAYOFF
YEAR PRINCIPAL INTEREST TOTAL BALANCE 2022 $298.00 $112.64 $410.64 $2,682.00 2023 $298.00 $80.46 $378.46 $2,384.00 2024 $298.00 $71.52 $369.52 $2,086.00 2025 $298.00 $62.58 $360.58 $1,788.00 2026 $298.00 $53.64 $351.64 $1,490.00 2027 $298.00 $44.70 $342.70 $1,192.00 2028 $298.00 $35.76 $333.76 $894.00 2029 $298.00 $26.82 $324.82 $596.00 2030 $298.00 $17.88 $315.88 $298.00 2031 $298.00 $8.94 $306.94 $0.00 TOTAL $2,980.00 $514.94 $3,494.94
$2,980 @ 3.00% Interest for 10 Years Avg Annual Payment $3,494.94 10 = $349.49 Avg Monthly Payment $349.49 12 = $29.12
PAST SINGLE FAMILY ASSESSMENT RATES
Project Assessment
19‐1 Street Rehabilitation (preliminary) $3,065.00 18‐1 Street Rehabilitation $2,557.80 17‐1 Street Rehabilitation $1,603.86 16‐1 Street Rehabilitation $1,401.64‐$1,675.54 15‐1 Street Rehabilitation $1,687.29‐$2,225.85 14‐1 Street Rehabilitation $2,356.97 13‐1 Street Rehabilitation $1,052.07 11‐1 Street Rehabilitation $1,324.27 10‐3 Silver Lane Reconstruction $1,894.51 10‐1 Street Rehabilitation $1,318.74
Neighborhood Informational Meeting February 27, 2020 Feasibility Study & Set Improvement Hearing Date March 10, 2020 Public Improvement Hearing CANCELLED March 24, 2020 Public Improvement Hearing May 12, 2020 Award Contract June 2020 Start Construction Summer 2020 Project Completion October 2020 Assessment Hearing September 2021
PROJECT 20‐1 SCHEDULE
RECOMMENDATIONS
- 1. Hold Public Improvement Hearing
- 2. Adopt Resolution
- Ordering Project 20‐1, 2020 Street Rehabilitation
- Approval of Project Plans and Specifications
- Authorization to Advertise for Bids