Project Presentation 23/02/2016 Organogram Education Funding - - PowerPoint PPT Presentation

Project Presentation 23/02/2016 Organogram Education Funding Agency (Funder) 3BM Education Partners ARK Schools LBHF (Project Management/Cost (School) (Client) Management) Bowmer & Kirkland Building Services (Contractor) Design


slide-1
SLIDE 1

Project Presentation 23/02/2016

slide-2
SLIDE 2

Organogram

Education Funding Agency

(Funder) Bowmer & Kirkland Building Services (Contractor) Design Consultants LBHF (Client)

3BM Education Partners

(Project Management/Cost Management)

ARK Schools (School) Sub Contractors Utility Contractors

slide-3
SLIDE 3

Overview of Proposed Works

Existing Site Plan Proposed Site Plan

slide-4
SLIDE 4

Proposed Ground Floor Plan

slide-5
SLIDE 5

Proposed First Floor Plan

slide-6
SLIDE 6

Proposed External Works

slide-7
SLIDE 7

3D Visuals

slide-8
SLIDE 8

Works Completed to date

Summary of works progress to date:

  • Stopping up of Hemlock Road/ The Curve
  • Installation of turning head
  • Creation of site compound
  • Installation of temporary classroom 1
  • Implementation of temporary access arrangements
  • Partial completion of utility diversions

* Works complete to Feb 2016

slide-9
SLIDE 9

Utility Diversion Update

  • National Grid (Gas)
  • All diversion works complete
  • UK Power Networks (Electric)
  • All diversion works complete
  • British Telecom (Phone/Broadband)
  • Diversion works 90% complete
  • Target completion March 2016
  • Thames Water (Sewer & Water)
  • Condition surveys completed for existing infrastructure
  • Sewer build over approval in principle received from Thames Water (Feb 16)
  • Sewer build over agreement currently being progressed
  • Mains water diversion works anticipated March 2016
  • Virgin Media (Phone/Broadband)
  • Enabling works complete (Duct installation)
  • Licence requested from TFL for foot path works (New cabinet provision) – Currently awaited
  • 3 Month customer notice period required prior to works commencing upon receipt of TFL licence
  • Works completion anticipated June 2016

*Note dates are provisional and subject to change/confirmation by statutory utility providers

slide-10
SLIDE 10

Anticipated Programme

Key Task Date Anticipated Statutory utility diversions complete June 2016 New Build works commence on site June 2016 Installation of temporary classroom 2 August 2016 Occupation of temporary classroom 2 September 2016 (start of term) External landscape works commence July 2017 Removal of temporary classroom 1 & 2 July 2017 (end of academic year) Completion of new build August 2017 Completion of external works August 2017 Occupation of facilities September 2017

* Note timescales anticipated but subject to confirmation and change

slide-11
SLIDE 11

Temporary Classroom Accommodation

  • Additional temporary classroom required for 2016/17 academic year
  • Additional classroom proposed on top of existing temporary classroom
  • Planning application submitted 11/02/2016
  • Planning determination anticipated end of April 2016
slide-12
SLIDE 12

Playground Wall

  • Request received from parents for removal of the low seating walls

located in the playground

  • Wall’s built as part of 2011 refurbishment and now fall within the

listed building curtilage

  • Informal advice seeked from LBHF Design & Conservation officer
  • Initial feedback provided verbally implies that the walls can be

removed, however would require reinstatement upon completion of the new build works

  • Written confirmation requested from planning officers prior to

removal works being undertaken

slide-13
SLIDE 13

St Katherine's Church MUGA

  • Application for permitted development submitted October 2016 to

LBHF planning department

  • Additional information requested by LBHF Planning Xmas 2016
  • Additional information provided as requested February 2016
  • Feedback awaited from LBHF in relation to acceptance of additional

information

  • Works presented to diocese board at the end of February 2016 to

commence consultation period (understood to be 8-12 weeks)

  • Anticipated timeframe for commencing works June 2016
  • New facilities likely to be available for 2016/17 academic year