ProtoDUNE Single Phase Beam Plug Nitrogen Gas System Installation Tim - - PowerPoint PPT Presentation

protodune single phase beam plug nitrogen gas system
SMART_READER_LITE
LIVE PREVIEW

ProtoDUNE Single Phase Beam Plug Nitrogen Gas System Installation Tim - - PowerPoint PPT Presentation

ProtoDUNE Single Phase Beam Plug Nitrogen Gas System Installation Tim Loew Lawrence Berkeley Lab January 12, 2017 Introduction Gas System Overview and Installation Timeline Phase I Install and secure external gas system components to


slide-1
SLIDE 1

ProtoDUNE Single Phase Beam Plug Nitrogen Gas System Installation

Tim Loew Lawrence Berkeley Lab January 12, 2017

slide-2
SLIDE 2

Introduction

  • Gas System Overview and Installation Timeline
  • Phase I

– Install and secure external gas system components to roof and secure through feedthrough.

  • Phase II

– Mount Beam Plug into End Wall Field Cage and Install in Cryostat.

  • Phase III

– Uncoil and connect external gas line to Beam Plug mounted inside the Cryostat.

2

slide-3
SLIDE 3

Beam Plug Nitrogen System (External)

3

Nitrogen Line Feedthrough Pipe into Detector Interior Locally Accessible Control Panel TCO Located adjacent to walkway BL BR Beam Window

slide-4
SLIDE 4

Beam Plug Nitrogen System (Internal)

4

Mounted Beam Plug Nitrogen Line Connection End Wall Field Cage End Wall Field Cage Local Control Panel

N2 gas from/to Control Panel

slide-5
SLIDE 5

beam

Phase I-III Installation Sequences

Phase III (Prior To Step 12B) Phase II (Prior To Step 5A)

5 Graphics Source: Gina Rameika. Note: Phase timing shown approximate.

beam Phase II Phase III Phase I Phase I Phase II Phase III Beam Plug Beam Plug

1/2017 8/2017 9/2017 12/2017 Phase I 11/2017 Phase II Phase III

A B

slide-6
SLIDE 6

Phase I (Exterior): August/September 2017

  • Install external NitrogenGas

System components and Local Control Panel on roof.

  • Secure Nitrogen Line through the

Feedthrough Pipe flange.

  • EHN1 Services Needed:
  • AC Power
  • House Nitrogen Line with a single

custom fit section. No purity

  • requirements. Low moisture

content preferred.

  • Slow Control Sensors(mV readout):
  • Temperature RTD (2X)
  • Pressure (2X)

6

Valve Cluster Local Control Panel Valve Cluster Local Control Panel

EHN1 N2 in N2 to BP N2 Vent

Dielectric Break

slide-7
SLIDE 7

Phase I (Interior): August/September 2017

  • Nitrogen Line temporarily

coiled and supported by a Runway Beam until Beam C is in its final configuration.

  • Nitrogen Line leak tested.
  • Clean Electrical Grounding

with Dielectric Break verified.

  • System installation and

testing duration: 1‐2 weeks

7

Runway Beam Until Phase III, the N2 Line is coiled, secured and stowed N2 Line feedthrough from/to Control Panel above N2 gas from/to Control Panel

slide-8
SLIDE 8

Phase II: November/December 2017

  • Beam Plug installed into End Wall

Field Cage in Clean Room outside

  • f cryostat.
  • Beam Plug and End Wall Field Cage

inserted into Detector together during Step 5A (slide 5).

8

Staging Clean Room Detector End Wall Field Cage with Beam Plug Mockup at Ash River Trial Assembly Beam Plug Mockup End Wall Field Cage

slide-9
SLIDE 9

Phase III: December 2017

  • Beam Plug and End Wall Field

Cage in position inside the detector.

  • Scissor Lift is used to access

Beam Plug location before north drift End Wall Field Cages are in their final configuration.

9

Scissor Lift at Ash River Trial Assembly

Image: Gina Rameika

Lift Platform location Beam Plug Coiled N2 Line from Phase 1

Scissor Lift Work Platform

EHN1 SP Cryostat Floor to Ceiling

slide-10
SLIDE 10

Phase III: December 2017

  • Nitrogen Line is uncoiled and

connected to the Beam Plug via metal seal Conflat flange.

10

Secure N2 Line Connection Point (CAD)

Phase III‐type of view from Ash River. (Will be within arms reach at EHN1.)

Secure N2 Line Connection Point (mockup) N2 gas from/to Control Panel N2 gas from/to Control Panel N2 gas to/from Beam Plug

slide-11
SLIDE 11

Conclusion

  • Gas System Overview and Installation Timeline
  • Phase I

– Install and secure external gas system components to roof and secure through feedthrough.

  • Phase II

– Mount Beam Plug into End Wall Field Cage and Install in Cryostat.

  • Phase III

– Uncoil and connect external gas line to Beam Plug mounted inside the Cryostat.

11