Santa Susana Field Laboratory RCRA Facility Investigation Report - - PowerPoint PPT Presentation

santa susana field laboratory rcra facility investigation
SMART_READER_LITE
LIVE PREVIEW

Santa Susana Field Laboratory RCRA Facility Investigation Report - - PowerPoint PPT Presentation

Santa Susana Field Laboratory RCRA Facility Investigation Report Review Group 2 NASA Area I and Northern Portion of NASA Area II May 18, 2009 Thomas M. Skaug, C.E.G. Engineering Geologist California Environmental Protection Agency


slide-1
SLIDE 1

Santa Susana Field Laboratory RCRA Facility Investigation Report Review Group 2 – NASA Area I and Northern Portion of NASA Area II

May 18, 2009 Thomas M. Skaug, C.E.G. Engineering Geologist California Environmental Protection Agency Department of Toxic Substances Control

slide-2
SLIDE 2

Today’s Discussion...

  • RFI objectives and scope of RFI review
  • Group 2 RFI (RFI-2) Report organization

and contents

  • Site conditions and site history
  • Preliminary RFI findings
  • Preliminary Recommendations

1

slide-3
SLIDE 3

RFI Objectives

  • Identify sources of chemical contamination, what

chemicals are involved, and the extent of their

  • ccurrence
  • Evaluate where chemical contaminants are,

where they go, and how they get there

  • Obtain sufficient info to complete a risk

assessment

  • Gather data needed to make decisions on

interim or final cleanup measures

2

slide-4
SLIDE 4

How was this RCRA Facility Investigation Performed?

  • Historical Review
  • Data Collection & Evaluation
  • Recommendations

3

slide-5
SLIDE 5

Historical Review

  • Tens of thousands of documents related to

SSFL Compiled (reports, photos, hand-written notes, employee interviews, etc.)

  • 4347 documents identified related to Group 2

Reviewed for evidence of chemicals used and possible release locations

  • Site reconnaissance

4

slide-6
SLIDE 6

Data Collection and Evaluation

  • Nature and extent

– Potential areas of concern chosen (historical review, visual reconnaissance, etc.) – Sampling to evaluate presence – “Step-out” sampling to evaluate extent – Sampling completed when we answer: What is it? How much is there? And What is the boundary?

5

slide-7
SLIDE 7

Data Collection and Evaluation (cont.)

  • Data compared to published risk-based

concentrations and SSFL background if risk assessment is needed

6

slide-8
SLIDE 8

Data Collection and Evaluation (cont.)

  • Ecological & Human Health Risk

– Methods in current SRAM followed – Receptors – resident, worker, recreational Risk assessment must be updated to comply with SB990

7

slide-9
SLIDE 9

What are RFI Site Action Recommendations?

  • Based on the report findings of the RFI Report, the

Responsible Parties (RPs) can: – Conclude there is not enough data to make a decision (data gaps) – Identify and recommend areas for further evaluation in the Corrective Measures Study (CMS). – Identify and recommend areas for “no further action” (NFA).

8

slide-10
SLIDE 10

RFI Site Action Recommendations

For Group 2:

  • No sites are recommended for NFA.
  • All RFI Sites have identified data gaps

– Work Plan – Public Review

  • All RFI Sites areas are recommended for further

evaluation in the CMS

9

slide-11
SLIDE 11

RFI Site Action Recommendations

  • This is a starting point: more chemicals might

be identified for inclusion into CMS when updated input parameters are applied:

– SB990-compliant parameters; – Updated background; – Additional characterization studies (data gaps)

The Final RFI Report must address ALL

  • utstanding issues.

10

slide-12
SLIDE 12

Why Review RFI Reports Now?

Is there value in reviewing the RFI reports now, since we are still waiting for SB990-compliant RBSLs, updated Background data set, etc?

  • Yes. Significant investigation activities have occurred over the

years, and reporting of the data warrants review to ensure we are capturing the “big picture” issues now, rather than later.

  • Conducting review now will result in timely, adequate

completion of the RFI, which will generate a complete data set for use in the risk assessment.

  • Follow up sampling will be conducted based on RFI review.

The next RFI-2 report issued will utilize the updated data set (including SB990-compliant parameters and updated background) to complete the risk assessment and provide a basis for recommendations for inclusion of sites into the Corrective Measures Study.

11

slide-13
SLIDE 13

RFI-2 Report

Available on DTSC-SSFL web site for public review: http://www.dtsc-ssfl.com/

  • The RFI-2 report is the 6th RFI Group Report

submitted

  • RFI Report consists of 3 volumes (~300 pages

text + ~1,200 tables + ~150 figures/drawings + thousands of pages of lab data)

12

slide-14
SLIDE 14

RFI report submittals

  • RFI Program Report is an important

companion document to all RFI reports

  • The Quality Assurance Project Plan and

SRAM are important supporting documents to all RFI reports

  • Eleven RFI “group area” reports will cover

the entire site (Groups 1A, 1B, and 2 through 10)

13

slide-15
SLIDE 15

“Operable Unit” Review

  • “Surficial Media” (SMOU) includes all

environmental media above unweathered bedrock

  • “Chatsworth Formation” (CFOU) includes all

unweathered bedrock and associated groundwater

  • The RFI Report addresses both Surficial Media

and Chatsworth Formation

14

slide-16
SLIDE 16

Surficial Media OU & Chatsworth Formation OU 15

slide-17
SLIDE 17

SSFL Regional Map

16

slide-18
SLIDE 18

NASA Land Ownership

NASA Area II (Former AFP 57) 409.5 Acres NASA LOX Plant (Former AFP 64) 41.7 Acres

17

slide-19
SLIDE 19

Surficial Media RFI Groups

18

slide-20
SLIDE 20

Group Area 2 – RFI Sites

slide-21
SLIDE 21

RFI Site Summaries

20

slide-22
SLIDE 22

Group 2 – Former LOX Plant

Former LOX Plant 21

slide-23
SLIDE 23

Former LOX Plant - History

  • Owned by the U.S. Air Force and
  • perated by Air Products, Inc. from

1955 until the late 1971

  • Liquid oxygen (LOX) was produced at

the site from liquefied air using a cryogenic process

  • Buildings and LOX tanks were

removed in the early 1970s, and the concrete foundations were removed in 1996

  • Sump and clarifier were excavated

and removed as part of the accelerated cleanup program in 1993

  • Asbestos and Drum Disposal Area

was removed in early 1990s

  • Debris containing asbestos was

removed from drainage ditch in 2007

slide-24
SLIDE 24
slide-25
SLIDE 25

Former LOX Plant – Nature & Extent

  • Samples collected between 1993 and 2008

– Soil matrix: 251 samples – Soil vapor: 262 samples

  • Sampling shows presence of metals, polycyclic aromatic

hydrocarbons (PAHs); Dioxins, Volatile Organic Compound (VOC) soil gases

  • Data gaps: Silver, Benzo(b)fluoranthene, Indeno(1,2,3-

cd)pyrene, Trichloroethene (TCE) in soil vapor

24

slide-26
SLIDE 26

Former LOX Plant – Risk Evaluation

  • The primary chemicals for the LOX Plant are:

– Barium, – Benzidine, and – Polycyclic Aromatic Hydrocarbons – VOCs in soil vapor.

25

slide-27
SLIDE 27
slide-28
SLIDE 28

Group 2 – Area 2 Landfill

Area 2 Landfill

slide-29
SLIDE 29

Area 2 Landfill – History

  • Unlined landfill operated

1955 – 1980

  • Unused fill material and

construction debris (asphalt, concrete, drums, scrap metal, timber, vegetation) were disposed

  • f in the upper flat portion

and the steep north-facing slope.

  • Near total re-vegetation of

the disturbed areas was

  • bserved in the 1988 and

1995 aerial photographs.

slide-30
SLIDE 30

29

slide-31
SLIDE 31

Area II Landfill – Nature & Extent

  • Samples collected between 1993 and

2008

– Soil Matrix: 145 samples – Soil Vapor: 83 samples

  • Sampling shows presence of Metals,

PAHs, SVOCs, Dioxins, and PCBs.

  • Data gaps: Copper, PCB-congeners,

PAHs, Benzene in soil gas

30

slide-32
SLIDE 32

Area II Landfill – Risk Evaluation

  • The primary concerns are

– PCBs – PAHs – Dioxins – SVOCs [di-n-butylphthalate and bis(2- ethylhexyl)phthalate] – Benzene in soil vapor

31

slide-33
SLIDE 33
slide-34
SLIDE 34

Group 2 – Expendable Launch Vehicle (ELV)

Expendable Launch Vehicle

slide-35
SLIDE 35

ELV - History

  • Bldg. 202 was Laser and Electro-Optical

System (LEOS) storage, a cafeteria, photo lab, and for manufacturing of harnesses for space shuttles.

  • Bldg. 203 involved the use of a Lead

Tinning Machine, Vapor Degreaser, Aqueous Cleaner, Sand Blaster, and machine tools.

  • Bldg 206 was originally tested rocket

engine components using LOX and petroleum-based fuels (RP-1 and JP-4), chemical storage, engine assembly and check, paint booth operations, machine shop, welding shop, steam cleaning

  • perations, equipment

storage, hazardous materials storage, and

  • ffice space. Wastes

were burned off in pond.

slide-36
SLIDE 36
slide-37
SLIDE 37
slide-38
SLIDE 38

ELV – Nature & Extent

  • Samples collected between 1993 and

2008

– Soil Matrix: 353 samples – Soil Vapor: 41 samples

  • Sampling shows presence of Metals,

PAHs, Dioxins, and three VOCs.

  • Data gaps: Metals, Dioxins, SVOCs,

VOCs; cis-1,2-DCE (soil vapor)

37

slide-39
SLIDE 39

ELV – Risk Evaluation

  • The primary chemicals are

– Mercury – Dioxins – TCE in soil vapor.

38

slide-40
SLIDE 40
slide-41
SLIDE 41

Group 2 – Former Incinerator, Ash Pile & Sewage Treatment Plant

Former Incinerator & Sewage Treatment Plant

slide-42
SLIDE 42

Former Incinerator & Ashpile - History

  • The Incinerator was a brick

structure approximately 10 feet by 8 feet with a 30-foot-high metal smokestack, surrounded by a 4-foot concrete apron.

  • Operational from the mid-1950s

through the 1970s. Waste from the Incinerator was deposited in an ash pile located in an unpaved area to the south of the Incinerator.

  • Paper, photographs, and trash

were burned at Building 2758.

  • Soil investigation identified lead

and silver exceeded the threshold limit concentration.

  • Ash pile was removed and

excavated in 1993

Former Ash Pile

slide-43
SLIDE 43

Group 2 – Former Incinerator, Ash Pile & Sewage Treatment Plant

slide-44
SLIDE 44

Sewage Treatment Plant - History

  • Below grade, concrete-lined plant
  • Operated from 1961 – 1987
  • Received cooling tower water, possibly

containing trace solvents / fuels, and sanitary sewage

  • An inactive leach field lies to the east of the

STP, and received waste from the ELV buildings (B211/202/203/206).

  • The plant used a comminutor, source

aeration unit, and clarifier where clarified effluent was removed from the top after solids settled to the bottom.

  • Settled sludge was removed for disposal and

treated water was pumped out and ultimately arrived in the Silvernale Reservoir.

slide-45
SLIDE 45
slide-46
SLIDE 46

Incinerator/STP – Nature & Extent

  • Samples collected between 1993 and

2008 –Soil Matrix: 222 samples –Soil Vapor: 61 samples

  • Sampling shows presence of Metals,

PCBs, PAHs, Dioxins; VOCs in soil vapor.

  • Data gaps: Metals, PCB-126, PAHs,

Dioxins, SVOCs, VOCs in soil vapor

45

slide-47
SLIDE 47

Incinerator/STP – Risk Evaluation

  • The primary chemicals are

– Barium – Dioxins – Tetrachloroethene (PCE) in soil vapor

46

slide-48
SLIDE 48
slide-49
SLIDE 49

Public Comment Period April 20 through June 4

Thomas M. Skaug, C.E.G. Department of Toxic Substances Control 8800 Cal Center Drive Sacramento, California 95826 tskaug@dtsc.ca.gov

48

slide-50
SLIDE 50

Questions??

49