STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS PFRC JANUARY 24, 2017 PROJECT UPDATE AND SCHEDULE | 1 PROJECT SCHEDULE 2016 2017 2018 2019 USE PERMIT 2/2017 CERT. OF APPROP. 2/2017 DESIGN DEV. CONST. DOCS.
PROJECT UPDATE AND SCHEDULE| 1
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 3
2016 2017 2018 2019
USE PERMIT
- CERT. OF APPROP.
DESIGN DEV.
- CONST. DOCS.
BUILDING PERMIT CONSTRUCTION SCHOOL OPEN
PROJECT SCHEDULE
2/2017 2/2017 Fall 2017
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 4
PROJECT MILESTONES
- Concept Design approved November 2015
- Schematic Design approved June 2016
- Use Permit submitted: September 8, 2016
- EA submitted: September 8, 2016
- Water Quality Impact Assessment submitted: September 15, 2016
- Certifj
cate of Appropriateness submitted: September 22, 2016
- Presenting to Commissions: (Fall/Winter 2016/2017)
- Resubmission of Use Permit / COA: December 21, 2016
- County Board (projected): March 2017
- Building Permit (projected): Fall 2017
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 5
STAKEHOLDER INVOLVEMENT
- 23 BLPC meetings
- 13 PFRC meetings
- 7 HALRB/DRC meetings/work sessions
- 2 Gallery Walks / Open Houses
- Additional meetings with:
- Community leaders
- Department of Parks and Recreation
- VDOT
- Arlington County
- School Board Members
USE PERMIT UPDATE | 2
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 7
USE PERMIT MILESTONES
- Use Permit: September 8, 2016 / December 21, 2016
- Environmental Assessment: September 8, 2016
- Water Quality Impact Assessment: September 15, 2016
- Certifj
cate of Appropriateness: September 22, 2016 / December 21, 2016
- Commission Presentations:
- E2C2 - September 26, 2016
- Urban Forestry - October 27, 2016
- HALRB - December 21, 2016
- Parks and Recreation - TBD
- Transportation - TBD
- Planning - TBD
- County Board - March 18, 2017
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 8
USE PERMIT COMMENT AND RESPONSE
- Stormwater approach
- Vacation Lane sidewalks
- Coordination with DPR
- Historic/COA
- Real Estate
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 9
STORMWATER MANAGEMENT PLAN
NO. DESCRIPTION DATE WWW.QUINNEVANS.COM REVISIONSDEPARTMENT OF ENVIRONMENTAL SERVICES
ARLINGTON, VIRGINIA
SCALE: DESIGNED: CHECKED: 4100 VACATION LANE, ARLINGTON, VA 22007STRATFORD MIDDLE SCHOOL
1 4 7 8 9 10 11STRATFORD MIDDLE SCHOOL RENOVATION & ADDITION
4100 Vacation Ln, Arlington, VA 22207
QEA # 31406600 USE PERMITWATER QUALITY DRAINAGE AREA MAP
AS NOTEDC-610
K.RYAN S.PANDISH A REVISION 12/21/2016 09/08/2016QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 10
VACATION LANE SIDEWALK
- EXISTING
- PROPOSED
EXISTING SIDEWALK PROPOSED SIDEWALK
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 11
NEW ADDITION
HISTORIC COMMITTEE UPDATE| 3
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 13
HISTORIC COMMITTEE
- Committee kickofg
was on January 11, 2017
- Determine how to best recognize history of site while respecting the
building/site design process and timeline
- T
ree stages:
- Exploration and Discovery
- Analysis and Evaluation
- Expression and Design
- Interpretive Planner to be chosen shortly
- Present concept to School Board in late spring/early summer 2017
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 14
SITE PLAN
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 15
TW 303.50 TW 306.50 TW 302.50 TW 306.50 TW 304.50 TW 303.50 TW 300.50 TW 299.50 TW 300.50 TW 302.50 TW 306.50 TW 306.50 2 9 4 . 2 9 1 . 6 TW 302.50
304 306 294 296 300 298 3 6 304 302 308 3 1 312 298 300 3029 5 . 2 TW 294.25
2 9 6 294 2 9 2 292TW 296.00 TS 291.75 BS 280.75
312 310 302 300 298 296 294 292 290 288 286 284 282TS 285 TW 291.17
290 290 288 286 2 8 4 282 280T W 2 9 4 . 2 5 TW 289.85 T 9 5 . 2
2969 5 . 1 9 7 . 7 9 7 . 7
OLD DOMINION ROAD
(26) PROPOSED BIKE RACKS STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. FIELD STONE MARKERS RECALL ORIGINAL PATH STUDENTS TOOK ON INTEGRATION DAY TO ENTER THE SCHOOL. SEE CHARACTER IMAGE 2/SHEET L2-0H. ADA PATH CHANGED TO FLAGSTONE AT POINTS WHERE IT CROSSES THE HISTORIC PATH. SEE CHARACTER IMAGE 2/SHEET L2.0H. LOW WALL WITH INTEGRATED SEATING, TYP. SEE CHARACTER IMAGE 2/SHEET L2.0H. STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. SEAT WALL WITH INTERPRETIVE SIGN INTEGRATED. SEE CHARACTER IMAGE 3/SHEET L2.0H. BIOFILTER CONCRETE RETAINING WALLS. SEE DETAIL 1/L4-1H. SEE DETAIL 2/L4-1H.
HISTORIC PATH
Peirce Mill, QEA
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 16
HISTORIC PATH
TW 303.50 TW 306.50 TW 302.50 TW 306.50 TW 304.50 TW 303.50 TW 300.50 TW 299.50 TW 300.50 TW 302.50 TW 306.50 TW 306.50 2 9 4 . 2 9 1 . 6 TW 302.50
304 306 294 296 300 298 3 6 304 302 308 3 1 312 298 300 3029 5 . 2 TW 294.25
2 9 6 294 2 9 2 292TW 296.00 TS 291.75 BS 280.75
312 310 302 300 298 296 294 292 290 288 286 284 282TS 285 TW 291.17
290 290 288 286 2 8 4 282 280T W 2 9 4 . 2 5 TW 289.85 T 9 5 . 2
2969 5 . 1 9 7 . 7 9 7 . 7
OLD DOMINION ROAD
(26) PROPOSED BIKE RACKS STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. FIELD STONE MARKERS RECALL ORIGINAL PATH STUDENTS TOOK ON INTEGRATION DAY TO ENTER THE SCHOOL. SEE CHARACTER IMAGE 2/SHEET L2-0H. ADA PATH CHANGED TO FLAGSTONE AT POINTS WHERE IT CROSSES THE HISTORIC PATH. SEE CHARACTER IMAGE 2/SHEET L2.0H. LOW WALL WITH INTEGRATED SEATING, TYP. SEE CHARACTER IMAGE 2/SHEET L2.0H. STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. SEAT WALL WITH INTERPRETIVE SIGN INTEGRATED. SEE CHARACTER IMAGE 3/SHEET L2.0H. BIOFILTER CONCRETE RETAINING WALLS. SEE DETAIL 1/L4-1H. SEE DETAIL 2/L4-1H.
A B C A A B B C C
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 17
BUILDING SECTION
- OPPORTUNITY FOR
COMMEMORATION AT HEART OF SCHOOL FEATURE WALL
CONSTRUCTION PHASING | 4
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 19
CONSTRUCTION PHASING
- Possible Scope for Early Construction Work:
- Expanded Vacation Lane parking lot
- Construction entrance at Old Dominion Drive
- Considerations
- Minimize impact to Stratford Program
- Field access during 2018 spring season
- Construction access and routes
- Separating school and construction zones
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 20
CONSTRUCTION SCHEDULE
- Construction Schedule Milestones
- GMP Fall 2017
- Early Work Phase - January 2018
- Construction Start - June 2018
- Completion - August 2019