Technical Presentation to City of Victoria Council June 14, 2010
With: Stafford Bandlow | Jonathan Yardley Architects | Wilkinson Eyre Architects | H.W. Lochner| Advicas Quantity Surveyors| Sharp and Diamond | CN Ryzuk & Associates
Technical Presentation to City of Victoria Council June 14, 2010 - - PowerPoint PPT Presentation
Technical Presentation to City of Victoria Council June 14, 2010 With: Stafford Bandlow | Jonathan Yardley Architects | Wilkinson Eyre Architects | H.W. Lochner| Advicas Quantity Surveyors| Sharp and Diamond | CN Ryzuk & Associates
With: Stafford Bandlow | Jonathan Yardley Architects | Wilkinson Eyre Architects | H.W. Lochner| Advicas Quantity Surveyors| Sharp and Diamond | CN Ryzuk & Associates
6/13/2010 2
6/13/2010 3
6/13/2010 4
6/13/2010 5
Seismic Design Category After M6.5 Earthquake After M8.5 Earthquake Lifeline No damage No collapse Repair needed Other No collapse Repair needed Replacement needed
6/13/2010 6
events to provide a point of reference for non-technical audience
6/13/2010 7
6/13/2010 8
6/13/2010 9
6/13/2010 10
multi-use trail with connection to Galloping Goose/ENR Trail Main bridge with 3 lanes, on street bike lanes, rail. Designed as a traffic calmed corridor. Pedestrian Sidewalk with connections to adjacent pathways Improved downtown approaches including sidewalks along west of Wharf St. Consolidated green space
6/13/2010 11
Elimination of “S” curve and install traffic signal Integration with Harbour Pathway Improved navigation channel in accordance with current regulations Establish trail head for Galloping Goose / Trans Canada Trail New Railway Station
6/13/2010 12
Road/Train/On-Street Bike Deck Sidewalk Multi-Use Trail 5.0 m 3 -3.0 m 1.8 m 1.8 m 5.0 m 2.5 m
6/13/2010 13
6/13/2010 14
Esquimalt
calming
closures)
6/13/2010 15
6/13/2010 16
6/13/2010 17
2011 Complete design & tender 2012 Remove rail bridge & procure/fabricate long lead time components; foundations 2013 Continue construction 2014 Complete construction & open new bridge 2015 Remove old roadway bridge
* Based on conventional delivery (Design-Bid-Build)
6/13/2010 18
Under Construction 2011/2012 2013/2014 Early 2015
6/13/2010 19
New multi-use trail bridge with connection to Galloping Goose/ENR Trail Rehabilitated railway bridge Rehabilitated existing road bridge with improved deck for bikes; new sidewalk decking Establish trail head for Galloping Goose / Trans Canada Trail Existing railway station Existing “S” curve
6/13/2010 20
No dedicated on-street bike lanes Existing downtown approach roads with improved sidewalk along Wharf Street Green space remains “Land- Locked” (similar on east) Navigation channel width is limited by existing bridges
6/13/2010 21
Road Deck, 3-3 m lanes Sidewalk 2.5m Rail Deck 5 m Multi-Use Trail Bridge 5 m
6/13/2010 22
6/13/2010 23
6/13/2010 24
6/13/2010 25
* Full closures of several month durations are anticipated for future rehabilitation works ** Assuming completion of construction in 2015
6/13/2010 26
Repair* Frequency Starting ** Paint touch-up and steel repairs 5 years 2020 Repaint and steel repairs 15 years 15 years 2030 Approach span concrete deck replacement Once 2035
6/13/2010 27
Repair Frequency of Repairs (years)
Replacement
Rehabilitation
Existing Bridges New Multi-Use Trail Bridge Annual Maintenance annually annually annually Engineering Inspections bi-annual bi-annual bi-annual Paint Touch-Up 10 5 10 Repairs to wearing surface 5 5
Repaint 20 15 20 Approach Span deck replacement
15 15
6/13/2010 28
2011 Complete design & tender 2012 Procurement/fabrication of long lead time components, site preparation, foundations 2013 Construct new multi-use trail bridge and continue with upgrade to existing bridge foundations 2014 Rehabilitate railway bridge 2015 Rehabilitate road bridge Early 2016 Open
* Based on conventional delivery (Design-Bid-Build)
6/13/2010 29
2011/2012 2013 2014 2015 Early 2016 Under Construction Detour
6/13/2010 30
6/13/2010 31
Cost Item 2008 Estimate Class “C” Estimate Difference Construction Items* Mobilization, site preparation, traffic management 1 3 +2 Demolition of existing bridges 3 3 New bridge 44 48 +4 Civil works (includes Telus duct, contaminated soil) 5 6 +1 Subtotal Construction 53 60 +7 Contingency (15%) 4 9 +5 Engineering 6 8 +2 Property 1 +1 Escalation, Financing, taxes 11 +11 Total Estimated Cost 63 89 +26
6/13/2010 32
* General conditions provided in detailed estimate distributed to other construction items to reflect bid numbers
6/13/2010 33
Scope Class “C” Estimate Base Scope 89 Scope Changes: Delete railway related components (on capital costs) 12 Reduce seismic to M6.5 (NOT RECOMMENDED) 10 Reduced Scope at M8.5 77
* Includes all costs associated with construction, contingency, engineering, escalation, financing, Federal and Provincial taxes.
6/13/2010 34
6/13/2010 35
6/13/2010 36
Cost Item MMM Class “C” Estimate Construction Items Mobilization, site preparation, traffic management 4 Structural (including painting) 25 Electrical/mechanical 14 New multi-use trail bridge 15 Multi-use trail paths and trail head 2 Detours 2 Subtotal construction 62 Contingency (25%) 14 Engineering 13 Property 1 Escalation, financing, taxes 13 Total Estimated Cost 103
* General conditions provided in detailed estimate distributed to other construction items to reflect bid numbers
6/13/2010 37
Scope Cost Base Scope 103 Scope Changes:
Delete multi-use trail bridge and detours but retain trail head improvements on downtown and Victoria West sides (will require full closure for 12 months)
25
Reduce seismic performance to M6.5 NOT RECOMMENDED
15
Terminate rail West of crossing and replace railway bridge deck to allow use as multi-use trail bridge.
2 Reduced Scope at M8.5 80
* Includes all costs associated with construction, contingency, engineering, escalation, financing, Federal and Provincial taxes
6/13/2010 38
6/13/2010 39
6/13/2010 40
6/13/2010 41
Full Closure (12 months): Downtown Business Vehicle Diversion/Travel Time Bus Diversion Costs n/a n/a n/a 10.3 1.6 1.5 Two Lanes Open (12 months): Downtown Business Vehicle Diversion/Travel Time Bus Diversion Costs n/a n/a n/a 2.6 0.4 1.5
6/13/2010 42
Full Scope Replacement Rehabilitation Full Scope, Total Project Cost 89 103 Life cycle cost in $2010 22 48 Present value of life cycle costs* 4 12 Schedule with full scope 4 years 5 years Economic impact with full scope N/A 5 Reduced Scope Replacement Rehabilitation Reduced Scope, Total Project Cost 77 80 Life cycle cost in $2010 22 42 Reduced scope life cycle costs* 4 10 Economic impact with reduced scope N/A 13 Schedule with reduced scope 4 Years 4 Years * Present Value of maintenance/repairs costs discounted over 100 years using a rate of 3.5%.
6/13/2010 43
* Comparison based on full scope for both Options
Project Objective Replacement Rehabilitation
100 year service life Y Y M 8.5 seismic performance Y Y Heritage conservation– existing bridge structure N Y Heritage conservation – site Y Y Dedicated multi-use path Y Y On-street bike lanes Y N Dedicated rail crossing Y Y 3 lanes for vehicles Y Y Dedicated sidewalk Y Y Eliminate “S” curve Y N Integration with existing and proposed pathways Y Partial Traffic calming Y Y Upgraded navigation channel Y N Consolidation of existing green space Y N
6/13/2010 44
New Structure The bridge concept proposed is considered technically appropriate. Existing Bridges – Rehabilitation Options
Cost Estimate The total cost projected for either a new or rehabilitation is considered reasonable.
6/13/2010 45
6/13/2010 46