Transportation Asset Management Webinar Series Webinar 34 Integrating PM2 Targets with the TAMP Sponsored by FHWA and AASHTO Webinar 34 October 10, 2018 FHWA-AASHTO Asset Management Webinar Series This is the 34 th in a webinar series
FHWA-AASHTO Asset Management Webinar Series
- This is the 34th in a webinar series that
has been running since 2012
- Webinars are held every two months,
- n topics such as off-system assets,
asset management plans, asset management and risk management, and more
- We welcome ideas for future webinar
topics and presentations
- Submit your questions using the
webinar’s Q&A feature
1
Welcome
2
- FHWA and the AASHTO Sub-Committee on Asset
Management are pleased to sponsor this webinar
- Sharing knowledge is a critical component of advancing
asset management practice
DOT PM2 Reporting DOT PM2 Target Setting
PM2 Targets and the TAMP
4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2019 2018 Initial TAMP Complete TAMP
Where are we now?
DOT PM2 Reporting DOT PM2 Target Setting
PM2 Targets and the TAMP
3
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2019 2018 Initial TAMP Complete TAMP
Where are we now?
MPO PM2 Target Setting
Learning Objectives
4
– Building working knowledge of key concepts and definitions relevant to transportation asset management – Beginning to apply this knowledge in the context of PM2 Targets and TAMPs to answer:
- What approaches are agencies taking to coordinate PM2 Targets with the
TAMP?
- What benefits can my agency expect by better integrating PM2 target setting
with the TAMP?
- What are key lessons-learned for agencies as they move forward with
developing their complete TAMPs?
- SHARE LESSONS LEARNED, IDEAS, KNOWLEDGE!!!
5
Webinar Agenda
2:00 Webinar Introduction and Overview Steve Gaj (FHWA) Hyun-A Park (Spy Pond Partners, LLC) 2:10 Caltrans Target Setting Approach Michael Johnson (Caltrans) 2:30 Maryland Experience Meredith Hill (Maryland SHA) 2:50 Wyoming Integration of Pavement and Bridge Targets with the TAMP Martin Kidner (Wyoming DOT) 3:10 Q&A and Wrap Up
Caltrans Target Setting Approach
Michael Johnson P.E. State Asset Management Engineer October 2018
California’s Regional Planning Partners
- 18 Metropolitan Planning
Organizations
- 26 Regional Transportation
Planning Agencies
California Pavement Inventory
Bridge and Pavement Target Setting Workshop | Slide 3
Note: *Road Miles (RM) is center lane miles ** Lane Miles (LM) represents the measures for the NHS Source: 2016 HPMS Data
2016 Total California Pavement Inventory 180,351 Road Miles (RM*) 402,466 Lane Miles (LM**)
State 14,776 RM 49,682 LM Local 165,574 RM 352,784 LM
State Non-NHS 6,319 RM 13,033 LM = 26% State State NHS 8,458 RM 36,649 LM = 74% State Local NHS 5,450 RM 19,427 LM = 6% Local Local Non NHS 160,124 RM 333,357 LM = 94% Local
NHS Target Setting
California Bridge Inventory
Bridge and Pavement Target Setting Workshop | Slide 4
Source: National Bridge Inventory (NBI) bridges Note: NHS Targets are required on NBI bridges, non-NBI bridges excluded Note: There are over 250 Local Agency owners of NHS bridges of which 87% own less than 10 bridges *Deck area in thousand square feet (KSF)
2017 Total California NBI Inventory 24,868 Bridges Deck Area – 325,870 KSF*
State 12,413 Bridges Deck Area – 252,566 KSF Local 12,455 Bridges Deck Area – 73,304 KSF
State Non-NHS 3,217 Bridges Deck Area= 17% State State NHS 9,196 Bridges Deck Area=83% State Local NHS* 1,629 Bridges Deck Area= 32% Local Local Non NHS 10,826 Bridges Deck Area= 68% Local
NHS Target Setting
- 1. Identify the inventory and current condition of NHS pavements
and bridges
- 2. Solicit expected 2 and 4 year targets from all NHS owners
- 3. Use a quantity weighted approach to develop a statewide
targets
Target Setting Approach
Click to edit Master title style
Example Calculation
- Caltrans solicited MPO input before establishing targets
- State of California targets reflect each agencies expectations
- The approach is transparent and inclusive
Summary
MARYLAND’S NHS ASSET MANAGEMENT
- Ms. Meredith Hill, Performance Planner
- MDOT & the System
- NHS in Maryland
- Targets and Projections
- Delivering the Final TAMP
- MDOT Asset Management
- Lessons Learned
ABOUT OUR (MDOT SHA) SYSTEM
SYSTEM PRESERVATION TRADEOFFS
$0 $100 $200 $300 $400 $500 $600 $700 $800 $900 $1,000 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Other Pavement and Bridges
Actual Projected
Million
Access Controls ADA Retrofit Bicycle Retrofit Bridge Replace & Rehab. Capital Equipment CHART Communications Commuter Action Improvements Crash Prevention Drainage Emergency Enhancements Environmental Compliance Environmental Preservation Guardrail End Treatment Intersection Capacity Neighborhood Conservation Noise Barriers Park-n-Ride Pedestrian Access to Transit Railroad Crossings Railroad Safety & Spot Rest Areas & Information Centers Resurfacing & Rehabilitation Safety & Spot Sidewalks Statewide Planning & Research TMDL Compliance Traffic Management Urban Reconstruction
MDOT SHA Program
NHS IN MARYLAND
NHS Owners
- MDOT SHA
- MDOT MAA
- MDTA
- ACoE
- NPS
- Counties
- Municipalities
- Parks
Commission
Partners
- FHWA MD
Division Office
- MPOs
DEVELOPING THE NHS STORY
Bridges
- MDOT SHA submits NBIS for non-federal
structures, only.
- Has historical records for non-federal
structures
- Mature BMS capable of reasonable non-
federal condition projections
Pavement
- MDOT SHA collects all I&C information for
the directional lane miles of the NHS, regardless of ownership
- Has historical records for IRI, cracking,
faulting, & rutting
- Mature PMS capable of reasonable
condition projections
PERFORMANCE PROJECTIONS - BRIDGES
http://arcg.is/1r04uH
PERFORMANCE PROJECTIONS - PAVEMENT
DELIVERING ON TPM AND TAM
Data Collection Content Development Review Submission Oct Nov Dec Jan Feb Mar Apr May Early June
- Leadership Directive
- Building the Team
- Increasing shared competencies
- Data and Information
- Incorporate vulnerability into
management systems and project development
- Balance increasing tradeoff realities
with state of good repair practice and commitments
MDOT ASSET MANAGEMENT GOALS
The Department Asset Management Program is focused on the following goals:
1.
Know What We Own – Develop & Maintain Accurate Asset Inventory and Information
2.
Know What Condition Our Assets are In – Implement Conditioning Protocols & Track Maintenance/Costs
3.
Establish Plan for Maintaining a State of Good Repair – Develop & Document Processes & Procedures
4.
Commit to Asset Management Practices – Educate and Train Workforce in AM Practices
5.
Develop a Framework & Guidance for Asset Management Software
6.
Integrate Asset Management into How We Do Business
Critical Infrastructure ✓ Pavement ✓ Large Structures ✓ Rail ✓ Tunnels ✓ Facilities ✓ Vehicle Fleet & Equipment ✓ IT Systems
QUESTIONS
Meredith Hill
Performance Planner MDOT SHA, Innovative Performance Planning Division 410-545-8739 mhill8@sha.state.md.us http://arcg.is/1r04uH
http://data.imap.maryland.gov/pages/mdot/
Wyoming Integration of Pavement and Bridge Targets with TAMP
Martin Kidner State Planning Engineer, WYDOT
Critical Communication
- How fast can you change the needle?
- Will your funding change predictably?
- How do you handle inflation?
10/10/18
2
Buckle up
Space-Time Continuum
- Understand time from decision to
reporting.
– Legislature provides new funds (July 2009) – Contracts let (August 2009) – Crushing and paving (Summer 2010) – Measure (NHS every other year, 2011) – Report to HPMS (April 2012)
- “instant” reaction is a three year delay
10/10/18
3
Buckle up
Construction and Contract Maintenance History
10/10/18
4
Buckle up
Effects of inflation, constant funding scenario
10/10/18
5
Buckle up
40% 50% 60% 70% 80% 90% 100% 2016 2021 2026 2031 2036 Year
Non-Interstate NHS Condition Projections 4% Inflation Rate
Good + Excellent Target
Treatments are not system wide
10/10/18
6
Buckle up
- We are treating about 10% of the
interstate pavements per year
- The change in condition is relatively
slow
Don’t Fall Behind
10 year projection begins to indicate the condition of long life assets
10/10/18
7
Buckle up
So What?
- 2 year outcomes are already in the
pipeline
- 4 year targets don’t adequately show
the trends
- Assets are long lived, and need to
project longer term. How do we indicate compliance with the TAMP?
10/10/18
8
Buckle up
Output versus Outcome
- Output example: dollars spent on
pavement treatment.
- Outcome example: number of 0.1 mile
segments changed from poor to good with the lowest life cycle cost.
10/10/18
9
Buckle up
Management Systems
10/10/18
10
Buckle up
- Wyoming’s management system
indicates miles of light, medium, and heavy (1S, 2S, 3S) pavement treatment per system type
- Track committed projects by system,
type of treatment, and validates locations
QUESTIONS?
Martin Kidner, WYDOT, Planning Engineer martin.kidner@wyo.gov (307)777-4411
10/10/18
Buckle up
11
Questions?
- Submit your questions using the webinar’s Q&A feature