Update 25 September 2019 Waimea Water; Damwatch Engineering; - - PowerPoint PPT Presentation

update
SMART_READER_LITE
LIVE PREVIEW

Update 25 September 2019 Waimea Water; Damwatch Engineering; - - PowerPoint PPT Presentation

Waimea Community Dam Update 25 September 2019 Waimea Water; Damwatch Engineering; Fulton Hogan Taylors 25/09/2019 Waimea Water Ltd 1 Waimea Dam is underway and progressing well Ground Breaking Ceremony 9 August 2019 24/09/2019 Waimea


slide-1
SLIDE 1

Waimea Community Dam Update

25 September 2019

Waimea Water; Damwatch Engineering; Fulton Hogan Taylors

Waimea Water Ltd 25/09/2019 1

slide-2
SLIDE 2

Waimea Dam is underway and progressing well

Ground Breaking Ceremony 9 August 2019

Waimea Water Ltd 2 24/09/2019

slide-3
SLIDE 3

Agenda

  • Design
  • Construction update
  • Environmental update
  • Q&A

Waimea Water Ltd 24/09/2019 3

slide-4
SLIDE 4

Design

  • Concrete Faced Rockfill Dam

Waimea Water Ltd 24/09/2019 4

Turitea Concrete Faced Rockfill dam. Palmerston North Constructed 1907, 1912, 1996 3-D model overlaying existing site topography

slide-5
SLIDE 5

Design Parameter

▪ Features:

  • 13 Mm3 (13 billion litre) reservoir; 53m high; 220m crest length; 430,000 m3 rock
  • Rockfill embankment selected as most robust to seismic loads and uses indigenous material
  • Concrete face membrane
  • Zoning of material in embankment allows for drainage paths to mitigate internal erosion
  • Grout curtain seals water migration around and beneath dam

▪ Earthquake:

  • Operating basis: No non-superficial damage and fully operational:

1:150 AEP (years)

  • Seismic evaluation basis: Retain reservoir & no-uncontrolled:

1:10,000 AEP (years)

  • GNS seismic assessment: 0.64g horizontal peak & 1.65g maximum spectral accelerations
  • Active faults 8 km and 12 km from site

Waimea Water Ltd 5 24/09/2019

slide-6
SLIDE 6

Design Parameter

▪ Flood:

  • Probable maximum flood (PMF):

1094 m3/s (18.6 Mm3 / 24 hour)

  • 100 year flood:

375 m3/s

  • 12 May 2019 1:50 year

250 m3/s (47 mm/hr) ▪ Operational flow

  • Operational flow:

2.2 m3/s

  • Environmental (min) flow and flushing flow:

0.5 m3/s and 5 m3/s

  • Maximum:

17 m3/s (1.5 mM3/d = 10% reservoir / day) ▪ Design Standards: NZSOLD / ANCOLD / ICOLD: Highest category (High PIC)

Waimea Water Ltd 6 24/09/2019

slide-7
SLIDE 7

Design

  • Damwatch supporting design enhancements and construction verification (PS-4)
  • Optimising zoning of rock fill materials to provide flexibility and robustness to geology
  • Optimised spillway design to de-risk construction and operations
  • Optimised plinth design and updated grout curtain specification
  • Mechanical and Electrical design progressing (hydropower compatible)

Waimea Water Ltd 7

2009: 5-9 2012: 10-14 2017: 15-17

24/09/2019

slide-8
SLIDE 8

Construction

  • Access Road: 5.5 km of 6.5 km complete.
  • Pig Flat bridges underway
  • Haul roads established
  • Concrete batching plant operational
  • Clearing Right Hand Abutment

Inspected and mapped top exposed section

  • Cutting down for Left Hand Abutment
  • Excavating for Left Hand plinth

Completed and cleaned for first 20m

  • River training to Left Hand side
  • Vegetation clearance, salvage and mulch underway

Waimea Water Ltd 8 24/09/2019

slide-9
SLIDE 9

Construction: Clearing LHS Abutment. As expected

Waimea Water Ltd 9 24/09/2019

slide-10
SLIDE 10

Construction: Clearing LHS Abutment. As expected

Waimea Water Ltd 10 24/09/2019

slide-11
SLIDE 11

Construction: Preparing for LHS Plinth. As expected

Waimea Water Ltd 11 24/09/2019

slide-12
SLIDE 12

Construction: Preparing for LHS Plinth. As expected

Waimea Water Ltd 12 24/09/2019

slide-13
SLIDE 13

Construction: Clearing RHS Abutment. As expected

Waimea Water Ltd 13 24/09/2019

slide-14
SLIDE 14

Construction: Clearing RHS Abutment. As expected

Waimea Water Ltd 14 24/09/2019

slide-15
SLIDE 15

Construction: Clearing RHS Abutment. As expected

Waimea Water Ltd 15 24/09/2019

slide-16
SLIDE 16

Construction: September to December 2019

  • Clear the RHS and LHS abutments and plinth cut. Rock anchors and slope stabilisation
  • Commence forming plinth LHS and RHS
  • Construct diversion bunds to move river away from RHS for culvert construction
  • Excavate for and commence forming culvert in RHS of riverbed
  • Continue vegetation clearance in reservoir footprint

Waimea Water Ltd 16 24/09/2019

slide-17
SLIDE 17

Environment and Sustainability

  • 164 Resource Consent conditions; Working 98 action items
  • Biodiversity Management Plan approved with 8 plans. BTAG

Onsite

  • 7/9 SCEMPS approved, implemented and being monitored
  • 4 Sediment Retention Ponds & 8 Decanting Bunds operating
  • Hydroseeding & mulching mitigates erosion and sedimentation
  • Fortnightly independent water quality monitoring complies
  • Continuous turbidity monitors guides river works
  • 2/4 rare plant species being moved (BMP #2)

Offsite

  • Ordering 10,000 plants and weed control for Rough Island

Waimea Water Ltd 17 24/09/2019

slide-18
SLIDE 18

Program

Waimea Water Ltd 18 12/09/2019

slide-19
SLIDE 19

SOI: We are doing what was said we would do

Waimea Water Ltd 19

Funding and Spend Forecast cost & schedule to complete

24/09/2019

slide-20
SLIDE 20

Waimea Water Ltd 20

Risk Management: 22% of Project Budget at Risk

SOI: We are doing what we said we would do

Compaction trials Further Borelogs Embankment design M&E Design Refine Grout Spec FM Preparedness

Identify Ownership Assess Mitigate Portfolio

Risk Register (56 27)

24/09/2019

slide-21
SLIDE 21

SOI: We are doing what we said we would do

Waimea Water Ltd 21

Health and Safety Compliance and Audit Late or urgent compliance issues:

24/09/2019

slide-22
SLIDE 22

More Information

Waimea Water Ltd 22 12/09/2019

slide-23
SLIDE 23

Q&A

Waimea Water Ltd 23

Questions? Waimea Water; Damwatch Engineering; Fulton Hogan Taylors

24/09/2019