Los Gatos Creek Bridge Replacement Project Oct 18. 2017 Agenda I. - - PowerPoint PPT Presentation

los gatos creek bridge replacement project
SMART_READER_LITE
LIVE PREVIEW

Los Gatos Creek Bridge Replacement Project Oct 18. 2017 Agenda I. - - PowerPoint PPT Presentation

Los Gatos Creek Bridge Replacement Project Oct 18. 2017 Agenda I. Project Description II. Project Benefits III. Challenges IV. Construction Update Project Location Located along Caltrain line In the City of San Jose Bounded by


slide-1
SLIDE 1

Los Gatos Creek Bridge Replacement Project

Oct 18. 2017

slide-2
SLIDE 2

Agenda

I. Project Description II. Project Benefits III. Challenges

  • IV. Construction Update
slide-3
SLIDE 3

Project Location

Located along Caltrain line

  • In the City of

San Jose

  • Bounded by

Park Avenue to the north and Interstate 280 to the south

slide-4
SLIDE 4

Los Gatos Creek Bridge

  • Owned by the Peninsula Corridor Joint Powers Board
  • MT1 owned by UPRR
  • Built in 1935
  • Does not meet existing current seismic safety standards
  • Has structural deficiencies
  • Southern timber span was

damaged by fire

  • Recent Flooding has

caused significant scour

slide-5
SLIDE 5

Project Elements

  • Demolish existing two-track bridge
  • Replace existing bridge with three new single track

bridges

  • Meet current safety and seismic codes
  • Include a tail track to maintain rail operations throughout

construction

  • Build a Retaining Wall
  • Widen Creek Channel
  • Facilitate City of San Jose future bike trail
slide-6
SLIDE 6

Project Benefits

slide-7
SLIDE 7

Project Benefits

  • Safe rail operations
  • Improves operations at the San Jose Diridon

Station

  • Addition of Tail Track
slide-8
SLIDE 8

Construction Challenges

slide-9
SLIDE 9
  • Phase I
  • Pre June 1 Work
  • Staging, fencing, temporary access roads, signal work, tail

track abutment work, and retaining wall work

  • Phase II – Dry Season Window
  • June 2017 – Aug. 2017 – Single Tracking on MT1
  • Tail track bridge construction, includes bridge foundation

and abutment work, pre-cast superstructure crane-in

  • Aug. 2017 – Oct. 2017 – Single Tracking on Tail Track
  • Existing bridge demolition, new Main Track 1 & 2 bridge

construction and in-creek site mitigation

  • Phase II -- Post Oct 2017
  • Main Track 1 & 2 track and signal work, out-of-creek site

mitigation, and site clean-up.

Construction Phases

slide-10
SLIDE 10

Construction Staging -- In Creek

slide-11
SLIDE 11

Unforeseen Conditions

slide-12
SLIDE 12

Water Diversion

Creek Water Diversion & Fish Relocation

slide-13
SLIDE 13

Limited Access

slide-14
SLIDE 14

Construction Status

slide-15
SLIDE 15

Progress in Field – Shoofly

slide-16
SLIDE 16

Progress in Field – MT 1 and MT2

slide-17
SLIDE 17

MT1 Bridge Construction

slide-18
SLIDE 18

Building Bents

slide-19
SLIDE 19

MT1 and MT2 Bridges

slide-20
SLIDE 20

Questions