DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. - - PowerPoint PPT Presentation
DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. - - PowerPoint PPT Presentation
DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. Kinsman P.E. Commander, Norfolk District Date: 30 Jan 2020 2 DEEP CREEK BRIDGE REPLACEMENT PROJECT Existing Bridge Part of the Dismal Swamp Canal project authorized by
2
DEEP CREEK BRIDGE REPLACEMENT PROJECT
Existing Bridge
- Part of the Dismal Swamp Canal project
authorized by River & Harbor Acts of 25 Jul 1912, 3 Mar 1925 and 3 July 1930
- Built in 1934; two-lane drawbridge operating in
conjunction with the Deep Creek Locks
- Owned and operated by the Norfolk District, U.S.
Army Corps of Engineers
- Considered functionally obsolete since 1996
Initial Appraisal
- Requires increasing maintenance and repair
- Key hurricane evacuation route
3
DEEP CREEK BRIDGE REPLACEMENT PROJECT
Proposed Replacement Bridge
- Construction Authorized by Water Resources
Development Act of 2007 (Public Law 110-114)
- Five-lane drawbridge along existing alignment
- Phased construction to accommodate traffic
- Two-lane eastbound bridge built south of existing
bridge
- Traffic shifts; existing bridge demolished
- Three-lane westbound bridge constructed
- Project ties into existing city roadway improvements
- To be built by Norfolk District, U.S. Army Corps of
Engineers; upon completion, ownership and
- peration and maintenance responsibilities will be
transferred to City of Chesapeake
4
DEEP CREEK BRIDGE REPLACEMENT PROJECT
5
BRIDGE REPLACEMENT PROJECT: TIMELINE
Congressional Authorization & Funding for USACE – Bridge Replacement Feasibility study
Bridge Design Complete 100% Chief’s Report signed; submitted to OMB & Congress USACE – project funding - Initial Replacement Assessment complete Congressional Project Authorization Construction Cost Estimate: $37.2M Congressional Appropriation: $12M Construction Cost estimate updated: $57.9M USACE: Project agreement signed with City of Chesapeake City agrees to provide $20M Real estate offers started Congressional Appropriation: $10M; USACE: real estate activities start
Limited Congressional Funding &
- ngoing bridge design
2015 –90% design
Construction Cost estimate updated: $48.7M Initial Meeting with Landowner’s Right-of-way acquisition began Citizen’s Information Meeting
1996 1998 2003 2007 2008 2015 2016 2017 2018 2019 2020
Update to Chesapeake City Council
6
Bottom Line Up Front
- All are frustrated with project delay
- Key actions required for contract award:
Complete acquisitions of land / easements Ensure completion of utility relocations: – Utility companies acquiring easements – Equipment must be moved prior to advertising contract Obtain additional funds: – Overall project cost estimate increased – Need additional $3.5M to award and administer the contract, $9.2M total
*Future Timeline Contingent on Real Estate, Utility Relocations, & Funding
WHAT IS TAKING SO LONG?
2020 2021 2024 2022 2023
Real estate acquisition, utility relocations; receive additional funding *Advertise construction contract *Award construction contract *Start construction – southern bridge *Estimated construction complete *Proposed traffic shift to new bridge *Demolition of old Deep Creek bridge *Construction of new northern portion of bridge
7
Acquisition Type: Fee: .9155 Acres Temporary Work Area Easement: 1.1605 Acres Drainage Ditch: .287 Acres
U.S. Government needs the lands and easements in order to award construction contract
- 40 parcels- rights required (combo of purchase, temp/perm easements)
- 32 parcels- rights acquired; one more likely soon
- 7 parcels starting condemnation process:
- Unable to reach agreement with landowners on “just compensation” (fair and reasonable)
- Congressionally mandated condemnation process – estimate 6-9 months
- Lengthier process; requires Department of Justice and Federal court
Ownership City of Chesapeake owned: 14 Chesapeake Public Schools owned: 1 US Government owned: 1 19 other owners - privately owned: 24 24 Privately Owned Parcels: 16 signed by owner 1 active negotiation 7 in condemnation Utility Relocation Agreements: Dominion Energy – signed Verizon – signed Columbia Gas – signed Cox Communications – working
WHAT IS TAKING SO LONG? ANSWER: REAL ESTATE
8
2003