White Creek Rd over Little White Creek Bridge Replacement Project - - PowerPoint PPT Presentation

white creek rd over little white creek
SMART_READER_LITE
LIVE PREVIEW

White Creek Rd over Little White Creek Bridge Replacement Project - - PowerPoint PPT Presentation

White Creek Rd over Little White Creek Bridge Replacement Project Public Meeting April 16, 2013 Project Team Town of Hoosick Louis Schmigel Highway Superintendent Keith Cipperly Town Supervisor Creighton Manning Engineering, LLP


slide-1
SLIDE 1

White Creek Rd over Little White Creek

Bridge Replacement Project Public Meeting April 16, 2013

slide-2
SLIDE 2

2

Project Team

Town of Hoosick

  • Louis Schmigel – Highway Superintendent
  • Keith Cipperly – Town Supervisor

Creighton Manning Engineering, LLP

  • Charles Tutunjian, PE – Project Manager
  • Tom Barrell, PE – Project Engineer
  • Alex Brown, IE – Assistant Project Engineer
slide-3
SLIDE 3

3

Meeting Agenda

  • Introduce the project team
  • Project Overview
  • Project goals and purpose
  • Project alternatives
  • Existing conditions
  • Recommended alternative
  • Next steps
  • Public Questions and Comments
  • Receive public input about the project
  • Address questions the community has about the project
slide-4
SLIDE 4

4

Project Location

slide-5
SLIDE 5

5

Design Report

  • Project Identification, Needs and Objectives
  • Preliminary Alternatives ‐ Engineering
  • Geometrics, Traffic, Safety, Drainage, Utilities, Right‐of‐Way, Pedestrians,

Costs

  • Environmental, Social and Economic Considerations
  • Environmental – Historical resources, Air Quality, Noise, Energy
  • Social ‐ Planning, Community, Emergency Services, Social Groups
  • Economic – Local Economy, Highway related businesses, Established

Business Districts

  • Indirect and Secondary Impacts
  • Evaluation and Comparison of Alternatives
slide-6
SLIDE 6

6

Project Goals

  • Increase the structural capacity of the crossing
  • Provide a structure with a 50‐year (minimum)

design life

  • Improve roadway geometry
slide-7
SLIDE 7

7

Alternatives

  • Do Nothing (Null Alternative)
  • Alternative 1
  • Complete Replacement on Improved Alignment
  • Alternative 2
  • Superstructure Replacement
slide-8
SLIDE 8

8

Existing Conditions

  • Deteriorated bridge deck
  • Deteriorated stringers
  • Load posted structure
slide-9
SLIDE 9

9

Existing Conditions

  • Deteriorated Substructure
  • Erosion behind wingwall
  • Non‐standard pipe bridge

rail

  • Broken bridge rail (safety

hazard)

slide-10
SLIDE 10

10

Existing Conditions

  • Uneven, cracked, and

patched pavement

  • Substructures constrict

stream

slide-11
SLIDE 11

11

Which Alternative is Preferred?

Alternative 1 – Complete Replacement

Removes kink in road and improves roadway geometry 50‐year design life No load posting

slide-12
SLIDE 12

12

Alternative 1 – Complete Replacement

slide-13
SLIDE 13

13

Alternative 1 – Complete Replacement

slide-14
SLIDE 14

14

Alternative 1 – Complete Replacement

  • Precast Concrete Con‐Span Arch Elevation
slide-15
SLIDE 15

15

Alternative 1 – Complete Replacement

  • Top of roadway view

Source: Google Earth image of Stone Way N in Seattle, WA

slide-16
SLIDE 16

16

Detour

  • Project will be built in one stage
  • If project were built in two stages, construction

cost would be approximately 25% more

  • Traffic will be detoured along Telford Rd
  • Telford Rd will be ½ mile longer commute
slide-17
SLIDE 17

17

Right of Way

  • Temporary easements will be required to

accommodate construction activities

  • Permanent easements will be required so the

town can have access to maintain the structure

  • Easements will extend up to 50 ft from the edge
  • f the existing road
  • All disturbed areas will be reconstructed with

topsoil and seed

slide-18
SLIDE 18

18

Project Funding

Construction Cost:

  • Approximately $850,000

Funding Breakdown:

  • 80% Federal
  • 20% Local
  • 15% New York State
  • 5% Town of Hoosick
slide-19
SLIDE 19

19

Schedule / Next Steps

  • Incorporate public comments into Alternatives
  • Final Design Report – May 2013
  • Design Approval – June 2013
  • ROW Acquisitions Complete – December2013
  • Detailed Design Complete – December 2013
  • Advertise for Construction – February 2014
  • Construction Start – May 2014
slide-20
SLIDE 20

20

Questions?

  • General comments or questions?
  • Specific concerns can be addressed individually.
  • You are encouraged to take a comment form and

submit it tonight, via email, or regular mail.

slide-21
SLIDE 21

21

We appreciate your time. We appreciate your time. Thank you! Thank you!