US 51 Stoughton Roundabout Hoel/Silverado, STH 138, and Roby Road - - PowerPoint PPT Presentation

us 51 stoughton roundabout
SMART_READER_LITE
LIVE PREVIEW

US 51 Stoughton Roundabout Hoel/Silverado, STH 138, and Roby Road - - PowerPoint PPT Presentation

US 51 Stoughton Roundabout Hoel/Silverado, STH 138, and Roby Road Alex Hagen, P.E. WisDOT Project Manager Public Information Meeting #2 March 12, 2020 Presentation Outline Project area Project purpose and need Proposed staging


slide-1
SLIDE 1

Alex Hagen, P.E.

WisDOT Project Manager

Public Information Meeting #2

March 12, 2020

US 51 Stoughton Roundabout Hoel/Silverado, STH 138, and Roby Road

slide-2
SLIDE 2

Presentation Outline

  • Project area
  • Project purpose and need
  • Proposed staging
  • Project schedule
  • Comments and questions
slide-3
SLIDE 3

Project Area

slide-4
SLIDE 4

Project Purpose and Need

  • Project Purpose

▪The purpose of the Hoel Avenue/Silverado Drive, STH 138, and Roby Road intersection improvements along US 51 is to provide a safe and efficient transportation system to serve present and long- term travel demand while minimizing disturbance to the environment.

  • Project Needs

▪Improve intersection safety (Roby Road has received HSIP funding) ▪Accommodate projected traffic volumes ▪Improve bicycle and pedestrian accommodations

slide-5
SLIDE 5

Alternatives – STH 138 & Hoel/Silverado

slide-6
SLIDE 6

Alternatives – Roby Road

slide-7
SLIDE 7

Proposed Staging

  • Projects will be constructed together.
  • Jackson Street signal between the two project areas will maintain

normal operation during construction.

  • We will review the staging concepts of each construction area.
slide-8
SLIDE 8

Proposed Staging – STH 138 and Hoel/Silverado

Stage 1

slide-9
SLIDE 9

Proposed Staging – STH 138 and Hoel/Silverado

Stage 2

slide-10
SLIDE 10

Proposed Staging – STH 138 and Hoel/Silverado

Stage 2B

slide-11
SLIDE 11

Proposed Staging – STH 138 and Hoel/Silverado

Stage 2C

slide-12
SLIDE 12

Proposed Staging – STH 138 and Hoel/Silverado

Stage 3

slide-13
SLIDE 13

Proposed Staging – STH 138 and Hoel/Silverado

Stage 4

slide-14
SLIDE 14

Proposed Staging – Roby Road

Stage 1

slide-15
SLIDE 15

Proposed Staging – Roby Road

Stage 2

slide-16
SLIDE 16

Proposed Staging – Roby Road

Stage 3A

slide-17
SLIDE 17

Proposed Staging – Roby Road

Stage 3B

slide-18
SLIDE 18

Proposed Staging – Roby Road

Stage 4

slide-19
SLIDE 19

Project Schedule

  • Spring 2022 – Begin Construction

▪ Plans will be ready for 2021 construction if funding becomes available.

slide-20
SLIDE 20

Comments and Questions

  • Questions?