Los Angeles Community College District Harbor College HARBOR TEACHER PREPARATORY ACADEMY (HTPA) Design Build Project Delivery January 13, 2015 PART 1 HTPA PROJECT DESCRIPTION HTPA Proposed Project Site N Existing HTPA Campus & Site


slide-1
SLIDE 1

Los Angeles Community College District Harbor College

HARBOR TEACHER PREPARATORY ACADEMY (HTPA)

Design Build Project Delivery January 13, 2015

slide-2
SLIDE 2

PART 1

HTPA

PROJECT DESCRIPTION

slide-3
SLIDE 3

HTPA Proposed Project Site

N

slide-4
SLIDE 4

Existing HTPA Campus & Site

slide-5
SLIDE 5

Existing HTPA Campus & Site

HTPA Classroom Modular Harbor College Storage Containers Basketball half court School Administration Modular

slide-6
SLIDE 6

Existing HTPA Campus & Site

Walkway and Playfield east of site Existing HTPA T

  • ilet Modular

Entrance to existing HTPA Campus and adjacent parking Existing Harbor Storage building

slide-7
SLIDE 7

HTPA Proposed Project Scope

11 Classrooms – 14,525 sf Performing Arts- Music and Drama Classroom – 2250 sf PE/ Athletics Ancillary- Aerobics, Office and Lockers – 3888 sf Library and Media Center – 2481 sf Multipurpose Room (with Practice Gym & Platform Stage) – 6356 sf Special Education – 600 sf Food Services – 2395 sf Administration- 2200 sf Health Offices- 975 sf Maintenance & Operations Office and Support- 838 sf

38,540 sf

slide-8
SLIDE 8

Harbor Storage Facility Scope

Storage for extra books, computers, tables, chairs– 5800 sf Secure Storage for records– 800 sf

6750 sf

slide-9
SLIDE 9

HTPA T

  • tal Authorized Project Budget

Estimate HTPA Building 38,540 sf cost/sf Storage Building 6750 sf cost/sf Total Construction Budget (Contingency not Incl.) Development Agreement (03/01/14) $371/sf $130/sf $15.18 M Development Agreement Project Budget (03/01/14) -$ 23,495,810

slide-10
SLIDE 10

Project Schedule Activity Start End Project Procurement Jan 2015 June 2015 Design June 2015 April 2016 Construction Dec 2016 May 2018 Contract duration- 46 months- 24 July 2014 to 24 May 2018

slide-11
SLIDE 11

PART 2

Current Status

  • Programming completed. Pending LAUSD approval.
  • RFQ development in progress. Release scheduled for

January 16, 2015

slide-12
SLIDE 12

PART 3

Risks

  • Student drop off areas are congested during construction
  • Schedule delays (Procurement / DSA)
  • Unforeseen hazardous materials
slide-13
SLIDE 13

PART 4

Next Steps

  • RFP release scheduled for February 16, 2015
  • BOT award for Design builder scheduled for June 10, 2015
  • FMP&OC Presentation