WIS 89 Main Street Topel Street to Madison Street Construction Kick-off Meeting Craig Hardy, PE WisDOT Project Manager February 12, 2019 INTRODUCTIONS PROJECT LOCATION MAP SCOPE OF WORK DETOUR ROUTE & CONSTRUCTION
INTRODUCTIONS PROJECT LOCATION MAP SCOPE OF WORK DETOUR ROUTE & CONSTRUCTION STAGING PROJECT SCHEDULE ACCESS DURING CONSTRUCTION TEMPORARY BUSINESS SIGNS
WHAT WisDOT CAN DO WHAT BUSINESSES CAN DO 2
Craig Hardy – WisDOT PM Jeremey White – WisDOT Designer / Construction
Inspector
Jim Oettinger – WisDOT Supervisor Chad Raschein – CGC – Project Leader
Mark LaLonde – LaLonde Contracting Eric Schmeling – LaLonde Contracting
3
4
WIS 89/ S. Main St. project includes new:
Storm sewer Watermain and sanitary sewer. Decorative street lighting along entire length Curb & gutter Sidewalk along both sides Concrete pavement 5
State Signed
Detour for Through Traffic & Trucks: I 94 to WIS 26 to US 18
6
HWY . 18 I-94
7
8
Vehicular access to businesses and residences
provided on WIS 89 only as needed during construction.
- Constricted work area, deep trenches and rough
pavement may damage vehicles – not preferred.
Businesses with alternate access are encouraged
to use that access throughout construction. Better for business to keep one consistent access point.
Contractor will coordinate in advance for driveway
closures.
9
10
THIS IS CONSTRUCTION
Sidewalk on one side of WIS 89 will remain in place
and open at most times. This only applies in areas where there is existing sidewalk.
Temporary crosswalks will be installed at
intersections outside the construction area along side streets. Temporary crosswalks will be installed crossing the work area at Lake St., Water St., Lake Park Pl., Keyes St., & Pinnacle Dr.
11
12
Temporary Pedestrian Barrier
13
14
Access to and from driveways will be limited,
especially during construction hours. PLAN AHEAD for your day and the next day.
For residents with limited mobility or special access
requirements, Contact Project Staff to discuss accommodations.
Advance notices will be given of planned closures. Emergency Vehicle Access will be maintained along
the project.
RESIDENT ACCESS DURING CONSTRUCTION
Approx. 72 hours notice prior to closure of
driveway access
Approx. 10 days notice prior to intersection
closures
Approx. 48 hours prior to sidewalk / utility
interruption
15
Driveways closed for approximately:
- 48 hours for utility installation (Cumulative, not
consecutive)
- 48 hours for roadway excavation
- 5 calendar days for concrete pavement
- 10 calendar days for curb and gutter, concrete driveway,
and concrete sidewalk.
16
17
18
FERRY DR.
- E. LAKE PARK PL.
GROVE ST. LAKE ST.
19
FERRY DR. GROVE ST. LAKE ST. WOODLAND BEACH RD.
20
- E. LAKE PARK PL.
WisDOT Traffic Control signs near the start of the detour
route to let drivers know they can still access local businesses.
Identify Alternate Business access routes Closer to construction complete permit for temporary
signs to identify size, material, and location of temporary business sign.
Handout maps showing alternate access and location of
business can help customers during construction.
21
22
Safe location, not creating an obstacle or an
- bstruction to visibility
Must mount on crash-safe supports Clear, simple message Encourage use of joint signs for groups of
businesses in the same area
Black lettering on white background, minimum
4” height, simple block-style font
Get permission of local authority for signs on
local roads
24
25
Field staff will be on site during construction for response
to questions/concerns affecting businesses.
Send weekly updates via email describing project
progress and upcoming activities.
WisDOT “In this Together” website 27
https://wisconsindot.gov/Pages/projects/in-together/default.aspx Project Website: http://wisconsindot.gov/Pages/projects/by- region/sw/89/default.aspx - update with construction website.
We will email this link to everyone who signs up for
- ur email update list, so please sign up today.
PLAN AHEAD Work together to devise a creative plan or
‘City Theme’ used to advertise business areas.
Work with City and other businesses to find
alternate access alternatives if needed
Advertise Designate one person to filter questions
through
PROJECTS COORDINATED TO MINIMIZE
DISRUPTION TO ALTERNATIVE ROUTES
- MAIN STREET PROJECT TO WORK IN
DOWNTOWN 1ST
- SOUTHERN SECTION OF MULBERRY PROJECT
CANNOT START UNTIL AFTER JUNE 1ST.
Craig Hardy, P.E., WisDOT Project Manager
- 608-216-3158, Craig.Hardy@dot.wi.gov
Chad Raschein, P.E., Consultant Project Leader
- 608-225-1364, craschein@cgcinc.net
34